File #: DC-3219    Version: 1
Type: Consent Action Status: Passed
File created: 3/8/2024 In control: Board of Commissioners
On agenda: 4/23/2024 Final action: 4/23/2024
Enactment date: 4/23/2024 Resolution #: 24-221
Title: Authorization To Execute Agreement Amendment No. 1033271A01 With Minnesota Department Of Transportation To Extend Project Deadline For Corridor Signal System Timing In City Of Eagan, County Project 26-56
Sponsors: Transportation
Attachments: 1. Project Location, 2. Agreement Amendment No. 1033271A01, 3. Financial Summary
DEPARTMENT: Transportation
FILE TYPE: Consent Action

TITLE
title
Authorization To Execute Agreement Amendment No. 1033271A01 With Minnesota Department Of Transportation To Extend Project Deadline For Corridor Signal System Timing In City Of Eagan, County Project 26-56
end

PURPOSE/ACTION REQUESTED
Authorize execution of Agreement Amendment No. 1033271A01 with Minnesota Department of Transportation (MnDOT) to extend project deadline for County Project (CP) 26-56 Signal Timing in the City of Eagan.

SUMMARY
To provide a safe and efficient transportation system, Dakota County is partnering with MnDOT on CP 26-56. The project has two components; construction which was completed in 2023 and traffic signal timing optimization that is currently moving forward. The traffic signal timing consists of developing and implementing timing optimization of 27 traffic signals along County State Aid Highway (CSAH) 26 (Lone Oak Road), CSAH 28 (Yankee Doodle Road), CSAH 31 (Pilot Knob Road), and CSAH 43 (Lexington Avenue) in the City of Eagan (Attachment: Project Location).
Agreement Amendment No. 1033271A01 (Attachment: Agreement Amendment No. 1033271A01) extends the agreement duration by one year to allow for the completion of the signal timing from July 30, 2024 to July 30, 2025. The amendment does not change the project funding, and the City of Eagan has no cost share for the signal timing.

RECOMMENDATION
recommendation
Staff recommends executing agreement amendment No. 1033271A01 with MnDOT for CP 26-56 and extending the project deadline to 7/30/2025 for the traffic signal timing.
end

EXPLANATION OF FISCAL/FTE IMPACTS
The 2024 Transportation Capital Improvement Program Adopted Budget contains a remaining budget of approximately $350,000. Sufficient funds exist to complete CP 26-56.

? None ? Current budget ? Other
? Amendment Requested ? New FTE(s) requested

RESOLUTION
body
WHEREAS, to promote a safe...