Legislation Details

File #: DC-2989    Version:
Type: Consent Action Status: Passed
File created: 1/9/2024 In control: Board of Commissioners
On agenda: 2/27/2024 Final action: 2/27/2024
Enactment date: 2/27/2024 Resolution #: 24-087
Title: Authorization To Award Bid And Execute Contract With Uhl Company, Inc. For Construction And Amend 2024 Facilities Capital Improvement Program Budget For Western Service Center Data Room Chiller Replacement Project
Sponsors: Parks, Facilities, and Fleet Management
Attachments: 1. Bid Tab, 2. Financial Summary

DEPARTMENT: Parks, Facilities, and Fleet Management

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Award Bid And Execute Contract With Uhl Company, Inc. For Construction And Amend 2024 Facilities Capital Improvement Program Budget For Western Service Center Data Room Chiller Replacement Project

end

 

RESOLUTION

body

WHEREAS, the 2024 Facilities Capital Improvement Program (CIP) Adopted Budget authorized the Western Service Center Data Room Chiller Replacement Project; and

 

WHEREAS, bid document and specifications were prepared by County staff and EDI-Dolejs, Inc.; and

 

WHEREAS, seven competitive bids were received on January 30, 2024; and

 

WHEREAS, Uhl Company, Inc. has submitted the low bid of $102,000; and

 

WHEREAS, staff has reviewed the qualifications of the bidder and recommends award to Uhl Company, Inc. as the lowest responsive and responsible bidder in an amount not to exceed $102,000 for the Western Service Center Data Room Chiller Replacement Project; and

 

WHEREAS, funding for the project is within the amended 2024 Facilities CIP Adopted Budget.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Parks, Facilities, and Fleet Management Director to execute a contract for the Western Service Center Data Room Chiller Replacement Project to Uhl Company, Inc. 9065 Zachary Lane North, Maple Grove, MN 55369, in an amount not to exceed $102,000, subject to approval by the County Attorney’s office as to form; and

 

BE IT FURTHER RESOLVED, That the 2024 Facilities Capital Improvement Program budget is hereby amended as follows:

 

Expense

Prior Project Savings (1001646)                     ($95,000)

Western Service Center Data Room                     $95,000

Chiller Replacement Project (2000007)                     

Total Expense                     $0

 

Revenue

Prior Project Savings (1001646)                     ($95,000)

Western Service Center Data Room                     $95,000

Chiller Replacement Project (2000007)                     

Total Revenue                     $0