Legislation Details

File #: DC-4279    Version: 1
Type: Consent Action Status: Passed
File created: 2/12/2025 In control: Board of Commissioners
On agenda: 3/25/2025 Final action: 3/25/2025
Enactment date: 3/25/2025 Resolution #: 25-158
Title: Authorization To Accept Donation Of Easements From Flint Hills Resources Pine Bend LLC For Mississippi River Greenway Rosemount East In City Of Rosemount, County Project P00109
Sponsors: Parks
Attachments: 1. Project Location Map, 2. Drainage and Utility Easement Map, 3. Valuation Spreadsheet, 4. FHR Recognition Letter
DEPARTMENT: Parks
FILE TYPE: Consent Action

TITLE
title
Authorization To Accept Donation Of Easements From Flint Hills Resources Pine Bend LLC For Mississippi River Greenway Rosemount East In City Of Rosemount, County Project P00109
end

PURPOSE/ACTION REQUESTED
Authorize the acceptance of the donation of necessary permanent easements for County Project (CP) P00109, Mississippi River Greenway (MRG) Rosemount East in the City of Rosemount.

SUMMARY
To provide a safe and efficient greenway system, Dakota County is proceeding with CP P00109. County Project P00109 is the construction of a 2.4-mile segment of the MRG in Rosemount and is the last remaining segment of the regional trail to be secured, designed, and constructed in order to connect the national MRG from Hastings to South St. Paul (Attachment: Project Location Map). County Project P00109 started construction in March of 2024, was substantially complete in November of 2024, and is projected to be completed in spring of 2025.

Flint Hills Resources Pine Bend LLC (FHR) owns property adjacent to Pine Bend Trail roadway in which the greenway alignment is located. By Resolution No. 23-063 (February 7, 2023), the board authorized the donation of permanent and temporary easements from FHR for the project. The total appraised value of the three parcels, represented as Parcels 1, 2, and 2A in Right of Way Map 360B, was $49,100.

Construction of the project started in March of 2024. During construction activities west of the tunnel, an area of FHR property that was unencumbered by a temporary or permanent easement was identified. This was a design error in the construction plans, and a new easement is required to complete the final utility work in this area to provide power for the tunnel lights (Attachment: Drainage and Utility Area Map).

Flint Hills Resources Pine Bend LLC has agreed to formally donate the required right of way to the County for the MRG Rosemount East project necessary to complete and maintain...