Legislation Details

File #: DC-5945    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 8/19/2026 In control: Board of Commissioners
On agenda: 9/1/2026 Final action:
Enactment date: Resolution #:
Title: Authorization To Rescind County Board Resolution No. 26-332 And Execute Use Agreement With Union Pacific Railroad And Progressive Rail To Improve Existing Railroad Crossing At Byllesby Bluff As Part Of Lake Byllesby Regional Park Master Plan Improvements
Sponsors: Facilities Management
Attachments: 1. Draft Private Crossing Agreement
Date Ver.Action ByActionResultAction DetailsMeeting MaterialsVideo
No records to display.

DEPARTMENT: Parks

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Rescind County Board Resolution No. 26-332 And Execute Use Agreement With Union Pacific Railroad And Progressive Rail To Improve Existing Railroad Crossing At Byllesby Bluff As Part Of Lake Byllesby Regional Park Master Plan Improvements

end

 

RESOLUTION

body

WHEREAS, the 2025 - 2029 Parks Capital Improvement Program Adopted Budget includes a project to formalize access and create basic trailhead amenities at project sites on the west side of Lake Byllesby Regional Park; and

 

WHEREAS, schematic design concepts were presented to and approved by the Dakota County Board of Commissioners by Resolution No. 26-113 (March 24, 2026); and

 

WHEREAS, the existing and only access to the Byllesby Bluff site crosses an existing railroad line owned by Union Pacific Railroad, leased and operated by Progressive Rail; and

 

WHEREAS, the two railroads have agreed to allow the existing crossing to remain a private, rural crossing as long as it is upgraded to two-way traffic and meets current railroad standards; and

 

WHEREAS, the required improvement work on and around the railroad tracks can only be completed by railroad-approved contractors through a formal Use Agreement; and

 

WHEREAS, pricing and scope for this required improvement work have been negotiated and can be constructed in the fall of 2026 if a Use Agreement is executed; and

 

WHEREAS, the negotiated pricing and scope included $267,500 for the physical work, but did not include $10,000 for the right to cross the railroad right of way and tracks until the final agreement was received by the County; and

 

WHEREAS, Resolution No. 26-332 (August 4, 2026) authorized execution of an agreement up to $275,000; and

 

WHEREAS, the total agreement amount is now $277,500.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners rescinds Resolution No. 26-332 (August 4, 2026); and

 

BE IT FURTHER RESOLOVED, That the Dakota County Board of Commissioners hereby authorizes the County Manager or delegate to execute a Use Agreement between Dakota County, Union Pacific Railroad, and Progressive Rail to govern the access and required improvement work at the Byllesby Bluff access; and

 

BE IT FURTHER RESOLVED, That the Dakota County Board of Commissioners hereby authorizes up to $277,500 for the access and construction work on and around the rail line to improve the crossing by a railroad-approved construction contractor named in the Use Agreement.

end

 

BACKGROUND

The Lake Byllesby Regional Park Master Plan Improvements project includes development of basic park trailhead facilities at three locations as shown in the Reference Map attachment. At the Byllesby Bluff site, this will include an aggregate driveway and parking lot for ten vehicles and a natural surface trail extending to a bird-watching structure. These amenities may be constructed in a future phase of the project. However, it is in the County’s best interest to complete the railroad-required improvements of the existing crossing to this site as soon as possible. Negotiations under the railroads’ processes have been productive, and a Use Agreement amenable to all parties can be completed in 2026. This will allow the work on and around the railroad tracks to be completed in the fall of 2026 and additional railroad-required improvements, such as paving, signage, and pavement markings, to be completed by the County in 2027. The County Board previously authorized up to $275,000 for this agreement. The final documents from the railroad now also include the right to cross the railroad right of way and tracks for an additional fee. The agreement amount will now be $277,500 to include the right to cross and the work to be performed by the railroad contractor.

 

RECOMMENDATION

recommendation

Staff recommends that County Board Resolution No. 26-332 (August 4, 2026) be rescinded. Staff also recommends the County Board approve the Use Agreement between Dakota County, Union Pacific Railroad, and Progressive Rail and the authorization of up to $277,500 under the agreement to govern the access and to complete work on and around the railroad tracks by a railroad-approved contractor set out in the Use Agreement.

end

 

FINANCIAL AND STAFFING IMPACTS

The 2025 Parks Capital Improvement Program includes $1,493,333 for Project 2000457 Lake Byllesby Regional Park Master Plan Improvements and is funded from the Minnesota Department of Natural Resources (MN DNR) Environmental and Natural Resources Trust Funds, Environmental Legacy Funds, and County Program Aid. This project budget includes funding for construction and can support the approval of this Use Agreement and the embedded construction work.

 

Project 2000457 Lake Byllesby Regional Park Master Plan Improvements

Funding Source

Total Approved Budget

Available Budget

MN DNR Environmental and Natural Resources Trust Fund

$1,120,000

$495,309

Environmental Legacy Fund

$341,436

$298,126

County Program Aid

$31,897

$7,706

Total

$1,493,333

$801,141

 

PREVIOUS BOARD ACTION

26-113; 3/24/26

26-332; 8/4/26

 

ATTACHMENTS

Attachment: Draft Private Crossing Agreement

 

CONTACT

Department Director: Niki Geisler

Author: Mike Lexvold