File #: DC-5252    Version: 1
Type: Consent Action Status: Passed
File created: 1/5/2026 In control: Board of Commissioners
On agenda: 3/24/2026 Final action: 3/24/2026
Enactment date: 3/24/2026 Resolution #: 26-130
Title: Authorization To Execute Third Contract Amendment With Ebert, Inc., dba Ebert Companies, For Wentworth Library Renovation
Sponsors: Facilities Management
Attachments: 1. Summary of Work Scope Changes

DEPARTMENT: Facilities Management

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Third Contract Amendment With Ebert, Inc., dba Ebert Companies, For Wentworth Library Renovation

end

 

PURPOSE/ACTION REQUESTED

Authorize execution of the third contract amendment with Ebert, Inc., dba Ebert Companies, to provide construction services for the Wentworth Library Renovation project.

 

SUMMARY

The 2025-2029 Facilities Capital Improvement Program Adopted Budget included a project to renovate the Wentworth Library in West St. Paul. The construction contract was awarded to Ebert Companies, in the sum of $3,578,700, by Resolution No. 25-146 (March 25, 2025).

 

In October 2025, when construction work was about 50 percent complete, staff executed the first contract amendment to Ebert Companies’ construction contract. This amendment increased the contract value by $47,112.94. In January 2026, when construction work was about 90 percent complete, a second contract amendment to Ebert Companies’ construction contract was executed. The second contract amendment increased the contract value by $121,771.50.

 

Construction work is now complete on this project. As work concluded, additional changes in work scope were discovered and resolved, resulting in requested contract changes totaling $43,367.92 and an extension of the substantial completion date by 20 working days. Combined with previous changes, this brings the total of construction contract changes to $212,252.36. The result is a new total contract value of $3,790,952.36 and a substantial completion date of February 20, 2026. A full list of all contract changes related to this requested third contract amendment can be found in Attachment: Summary of Work Scope Changes.

 

In comparison to the original construction contract value of $3,578,700, total changes are just under six percent which is consistent with the total percent increase observed on County projects of this size and complexity.

 

RECOMMENDATION

recommendation

Staff recommends authorizing a third contract amendment with Ebert Companies to increase the value by $43,367.92 for reimbursement of known construction changes and to add 20 working days to the completion schedule for the Wentworth Library Renovation project. This will increase the total contract value to $3,790,952.36 and extend the substantial completion date to February 20, 2026.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The Facilities Capital Improvement Program includes $7,400,000 for project 2000259 Wentworth Library Design and Renovation. There is sufficient project budget available to fund the third contract amendment with Ebert Companies.

 

Funding Source

Total Approved Budget

Available Budget

County Debt

$7,400,000

$1,632,945

Total

$7,400,000

$1,632,945

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, the 2025 Capital Improvement Program Adopted Budget for the Wentworth Library Renovation project is a total of $7,400,000; and

 

WHEREAS, by Resolution No. 25-146 (March 25, 2025), the County Board approved the original contract with Ebert, Inc., dba Ebert Companies, in the sum of $3,578,700; and

 

WHEREAS, in October 2025, staff executed the first contract amendment totaling $47,112.94 to amend the work scope; and

 

WHEREAS, in January 2026, staff executed the second contract amendment totaling $121,771.50 to amend the work scope; and

 

WHEREAS, upon construction completion, a third contract amendment is being requested to increase the contract by $43,367.92 and to add 20 working days to the completion schedule; and

 

WHEREAS, the total authorized contract amendments to this contract would then be $212,252.36 for reimbursement of known construction change orders on the project, for a new total contract value of $3,790,952.36; and

 

WHEREAS, the new substantial completion date of the construction contract will be February 20, 2026; and

 

WHEREAS, there are sufficient funds within the approved project budget for this amendment.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Facilities Management Director to execute a contract amendment with Ebert, Inc., dba Ebert Companies, 23350 County Road 10, Corcoran, MN 55357, in an amount not to exceed $43,367.92 and to add 20 working days to the schedule, for a maximum contract total not to exceed $3,790,952.36 subject to approval by the County Attorney’s office as to form.

end

 

PREVIOUS BOARD ACTION

25-146; 03/25/25

 

ATTACHMENTS

Attachment: Summary of Work Scope Changes

 

BOARD GOALS

   Thriving People        A Healthy Environment with Quality Natural Resources

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Mike Lexvold

Author: Trish Bremer