Title: Authorization To Execute Joint Powers Agreement With City Of Rosemount For Rosemount Greenway: Dunmore Segment
Sponsors: Parks
Attachments: 1. Area Map, 2. Project Map

DEPARTMENT: Parks

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Joint Powers Agreement With City Of Rosemount For Rosemount Greenway: Dunmore Segment

end

 

PURPOSE/ACTION REQUESTED

Authorize execution of a joint powers agreement (JPA) with the City of Rosemount (City) for the Rosemount Greenway: Dunmore segment.

 

SUMMARY

By Resolution No. 12-359 (July 31, 2012), the Rosemount Greenway Master Plan (Master Plan) was adopted by the Dakota County Board of Commissioners. The master plan established a preferred alignment for the Rosemount Greenway between Lebanon Hills Regional Park and Spring Lake Park Reserve via downtown Rosemount. (Attachment: Area Map)

 

The City, in coordination with private development, secured right of way as well as the initial grading for the trail portion of trail within Dunmore Development. The City has recently completed the 95 percent design for the trail gap with the intention to bid the project in the spring of 2025. (Attachment: Project Map)

 

The proposed JPA includes the roles and responsibilities and associated cost to complete the Dunmore segment. The total cost of the project, including project delivery costs, is estimated at $510,000. The City is leading the project and providing design and construction management estimated at $60,000. The estimated County cost is $450,000 for all construction elements, including a 10 percent contingency.

 

This greenway collaborative project is consistent with current cost-share practice for city-led greenway projects. Dakota County and the City of Rosemount will establish a Supplemental Maintenance Agreement (SMA) when the Rosemount Greenway is completed between Lebanon Hills Regional Park and Central Park or completed to Flint Hills Park via downtown.

 

RECOMMENDATION

recommendation

Staff recommends that Dakota County execute a JPA with the City of Rosemount for the Rosemount Greenway: Dunmore segment for the period of 4/01/2025 - 12/31/2026.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

Dakota County’s total share of the cost of the JPA is estimated to be $450,000. Sufficient funding has been authorized in the Parks Capital Improvement Program.

 

  ☐ None              ☒ Current budget              ☐ Other        

  ☐ Amendment Requested                           ☐ New FTE(s) requested

 

RESOLUTION

body

WHEREAS, by Resolution No. 12-359 (July 31, 2012), the Dakota County Board of Commissioners adopted the Rosemount Greenway Master Plan; and

 

WHEREAS, the master plan established a preferred alignment for the Rosemount Greenway between Lebanon Hills Regional Park and Spring Lake Park Reserve via downtown Rosemount; and

 

WHEREAS, the City, in coordination with private development, secured right of way as well as the initial grading for the trail portion of trail within Dunmore Development; and

 

WHEREAS, the City of Rosemount is leading the design, bidding, and construction management as their contribution towards the cost share; and

 

WHEREAS, Dakota County will reimburse the City of Rosemount 100 percent of the total project construction costs; and

 

WHEREAS, the total estimated project cost is $510,000, including project delivery; and

 

WHEREAS, the total estimated construction cost is $450,000, including a 10 percent contingency; and

 

WHEREAS, a joint powers agreement between the County and the City describing roles and responsibilities and associate costs is required; and

 

WHEREAS, sufficient revenues are available in the Parks Capital Improvement Program; and

 

WHEREAS, the future Supplemental Maintenance Agreement will be created to include ongoing maintenance and operations for project extents upon project completion of trail between Lebanon Hills Regional Park and Central Park in downtown Rosemount or completed to Flint Hills Park via downtown.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Physical Development Director, or their designee, to execute a joint powers agreement with the City of Rosemount to reimburse the City for costs associated with the Rosemount Greenway: Dunmore segment for the period of April 1, 2025, through December 31, 2026, subject to approval by the County Attorney’s Office as to form.

end

 

PREVIOUS BOARD ACTION

None.

 

ATTACHMENTS

Attachment: Area Map

Attachment: Project Map

 

BOARD GOALS

   ☒ A Great Place to Live                                          ☐ A Healthy Environment     

   ☐ A Successful Place for Business and Jobs         ☐ Excellence in Public Service

 

CONTACT

Department Head: Niki Geisler

Author: John Mertens