File #: DC-4471    Version: 1
Type: Consent Action Status: Passed
File created: 4/7/2025 In control: Board of Commissioners
On agenda: 5/20/2025 Final action: 5/20/2025
Enactment date: 5/20/2025 Resolution #: 25-251
Title: Authorization To Execute Fourth Contract Amendment With Ebert, Inc. dba Ebert Companies For Law Enforcement Center Integrative Health Unit Addition
Sponsors: Facilities Management
Attachments: 1. Summary List of Changes for Final Amendment

DEPARTMENT: Facilities Management

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Fourth Contract Amendment With Ebert, Inc. dba Ebert Companies For Law Enforcement Center Integrative Health Unit Addition

end

 

PURPOSE/ACTION REQUESTED

Authorize execution of a fourth and final contract amendment with Ebert, Inc., dba Ebert Companies for the construction of the Law Enforcement Center’s (LEC) Integrative Health Unit (IHU) Addition. Board action is required as the value of total amendments after initial authorization of the contract execution exceeds a policy limit of $250,000.

 

SUMMARY

The LEC IHU Addition project has been under construction for 18 months and is now complete. The construction contract was awarded to Ebert Companies in the sum of $10,573,800 by Resolution No. 23-379 (August 29, 2023). Three contract amendments have already been executed, which changed the completion date and included $510,148.94 in increased work. This fourth and final proposed set of changes totals $290,512.87 and requires Board approval because it exceeds the extended limit of the original contract authority. The proposed items are enumerated in Attachment: Summary List of Changes for Fourth Amendment.

 

In this action, staff is requesting a fourth contract amendment with Ebert Companies in the sum of $290,512.87 for construction improvements made at the LEC IHU for County Board authorization. These cost increases to the construction contract will be paid for with reserved funds remaining within the original project budget. This amount is slightly less than was forecasted in the last Board action for this contract. The last engineer’s estimate for construction including post-award changes was $11,800,000. Following this final amendment, construction will be completed roughly $425,000 under budget.

 

RECOMMENDATION

recommendation

A total of $510,148.94 in contract amendments has already been authorized by Resolution No. 24-460 (September 24, 2024). Staff recommends authorizing a fourth contract amendment with Ebert Companies, in the sum of $290,512.87 for construction improvements made at the LEC IHU. This brings the total authorized contract amendments to this contract to $800,661.81 and the new contract value to $11,374,461.81.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

Funds totaling $14,400,000 were included in the earlier adopted Capital Improvement Program budget for the design and construction of the LEC IHU Addition. Sufficient funds within the project (1001292) budget are available for this amendment.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, the 2023 Capital Improvement Program (CIP) Adopted Budget, as amended for the Law Enforcement Center (LEC) Integrative Health Unit (IHU) Addition project, is a total of $14,400,000; and

 

WHEREAS, by Resolution No. 23-379 (August 29, 2023), the County Board approved the original contract in the sum of $10,573,800 with an award to Ebert, Inc., dba Ebert Companies; and

 

WHEREAS, a first (no cost) contract amendment was formally executed by way of that authorization to establish a construction completion deadline of late-February 2025; and

 

WHEREAS, with the original contract authorization, staff was also authorized to execute up to $250,000 worth of post-award changes; and

 

WHEREAS, $247,756.03 in a second contract amendment has already been formally executed by way of that authorization; and

 

WHEREAS, an additional $262,392.91 worth of post-award changes were authorized to complete a third contract amendment to the contract with Ebert Companies by Resolution No. 24-460 (September 24, 2024); and

 

WHEREAS, an additional $290,512.87 worth of post-award changes are requested for authorization to complete a fourth contract amendment to the contract with Ebert Companies; and

 

WHEREAS, these project cost increases to the construction contract will be paid for with uncommitted funds available within the CIP budget for this project; and

 

WHEREAS, the total authorized contract amendments to this contract would then be $800,661.81 for reimbursement of all construction change orders on the project; and

 

WHEREAS, sufficient funds within the CIP budget for the project (1001292) are available for this amendment.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Facilities Management Director to execute a contract amendment with Ebert, Inc., dba Ebert Companies, 23350 County Road 10, Corcoran, MN 55357 in an amount not to exceed $290,512.87 for a total maximum contract total not to exceed $11,374,461.81, subject to approval by the County Attorney’s office as to form.

end

 

PREVIOUS BOARD ACTION

23-379; 08/29/23

24-460; 09/24/24

 

ATTACHMENTS

Attachment: Summary List of Changes for Fourth Amendment

 

BOARD GOALS

   Thriving People        A Healthy Environment with Quality Natural Resources

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Mike Lexvold

Author: Mike Wiese