Title: Authorization To Execute Fiber Optic Indefeasible Right To Use Agreement With Independent School District 196
Sponsors: Information Technology
Attachments: 1. ISD#196 Fiber IRU

DEPARTMENT: Information Technology

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Fiber Optic Indefeasible Right To Use Agreement With Independent School District 196

end

 

PURPOSE/ACTION REQUESTED

Authorize the Deputy County Manager to execute a Fiber Optic Indefeasible Right to Use Agreement (IRU) with Independent School District 196 (ISD 196) for use of unused fiber in the Dakota County owned institutional network backbone.

 

SUMMARY

Independent School District 196 desires to obtain the use of twelve fibers from Dakota County to connect to Emerald Trail Elementary and two fibers to provide redundancy, as described in the attached agreement. To facilitate fiber optic network expansion, and in accordance with our established practice of government entity collaboration, the unused fiber optic cables are available for this purpose.

 

The term of the IRU is ten years (2025 through 2035) with two optional five-year renewals that the parties will determine at that time.

 

RECOMMENDATION

recommendation

Staff recommends the County Board authorize the Deputy County Manager to execute an IRU with ISD 196 for use of the Dakota County Institutional Network.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

ISD 196 agrees to pay the County $65 per pair/mile/month for use of twelve strands of fiber optic cable. This fee totals $104,452 over the ten-year agreement.  Dakota County will be responsible for all costs of maintenance, locates, breaks, and fixes on the fiber.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, Independent School District 196 desires to obtain the use of twelve fibers from Dakota County to connect to Emerald Trail Elementary and two fibers for redundancy, as described in this Agreement; and

 

WHEREAS, Dakota County has unused fiber available that was previous constructed; and

 

WHEREAS, a Fiber Optic Indefeasible Right to Use Agreement with Independent School District 196 is required for use of County fiber optic cable; and

 

WHEREAS, pursuant to the proposed Agreement, ISD 196 will pay Dakota County $65 per pair per mile per month for use of twelve strands of fiber optic cable and Dakota County will be responsible for all costs of maintenance, locates, breaks, and fixes on the fiber.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Deputy County Manager to execute an IRU with Independent School District 196 for use of twelve strands of Dakota County-owned Institutional Network Backbone, subject to approval by the County Attorney’s Office as to form.

end

 

PREVIOUS BOARD ACTION

None.

 

ATTACHMENTS

Attachment: Fiber IRU

 

BOARD GOALS

   Thriving People        A Healthy Environment with Quality Natural Resources

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Dan Cater

Author: Dan Ferber