WHEREAS, to promote a safe and efficient transportation system, Dakota County is proceeding with County Project (CP) 63-33, County State Aid Highway (CSAH) 63 (Delaware Avenue) reconstruction in the cities of Mendota Heights and West St. Paul; and
WHEREAS, CP 63-33 will reconstruct CSAH 63 from Marie Avenue to Trunk Highway 149 (Dodd Road), including roadway modernization, intersection and safety improvements, stormwater facilities, and new, separated pedestrian and bicycle facilities; and
WHEREAS, acquisition of easements necessary to construct CP 63-33 has proceeded over the past year, with easements on 74 parcels acquired to date through negotiation or condemnation; and
WHEREAS, negotiations for acquisition of easements on one parcel are continuing; and
WHEREAS, significant expenses for right of way acquisition remain, including settlements, condemnation hearings, and building demolition; and
WHEREAS, a budget amendment to the 2026 Transportation Budget is necessary to complete acquisition of right of way for CP 63-33 and proceed into construction; and
WHEREAS, staff recommends increasing the budget of CP 63-33 by $673,714.
NOW, THEREFORE, BE IT RESOLVED, That the 2026 Transportation Capital Improvement Program Budget is hereby amended as follows:
Expense
County Project 63-33 $673,714
Total Expense $673,714
Revenue
County State Aid Highway $572,657
City Local Share $101,057
Total Revenue $673,714
end
BACKGROUND
Dakota County is advancing County Project (CP) 63-33 (Attachment: Project Location Map), with construction anticipated to begin in winter 2027 and continuing through fall 2028. Design is substantially complete, and advertisement for construction bids is expected later this year.
Acquisition of right of way for CP 63-33 is a significant part of the overall project effort and is nearing completion. Due to the volume of parcels required and the complexity posed by some, Transportation and Real Estate staff elected to seek consultant services for negotiation and acquisition of easements. The County retained Henning Professional Services as a subconsultant to Kimley-Horn and Associates, Inc., the design consultant for the project. The fee for acquisition services totaled $1,021,475. Remaining costs for right of way acquisition total $1,032,000, including settlements on remaining acquisitions, expenses for commissioner viewings and condemnation hearings, and demolition costs on a property purchased in fee. An amendment to the project budget is required to acquire the remaining easements and associated expenses.
RECOMMENDATION
recommendation
Staff recommends authorization to amend the 2026 Transportation Budget in the amount of $673,714 to complete right of way acquisitions and related expenses for CP 63-33.
end
FINANCIAL AND STAFFING IMPACTS
The 2026 Transportation Capital Improvement Program Budget includes $3,902,916 for CP 63-33 Reconstruction Marie to TH149, with $358,286 of unencumbered funds. The requested amendment would commit $572,657 in County State Aid Highway (CSAH) funding and $101,057 in city funding in accordance with current 2040 Transportation Plan cost share policies. The requested amendment would increase the current approved project budget by $673,714.
Current Approved Budget - 1001585 T63033 Reconstruction of Marie to TH149
|
Funding Source |
Total Approved Budget |
Available Budget |
|
CSAH Funds |
$3,343,533 |
$304,543 |
|
City Funds |
$559,383 |
$53,743 |
|
Total |
$3,902,916 |
$358,286 |
Proposed Amended Budget - 1001585 T63033 Reconstruction of Marie to TH149
|
Funding Source |
Total Approved Budget |
Available Budget |
|
CSAH Funds |
$3,916,190 |
$877,200 |
|
City Funds |
$660,440 |
$154,800 |
|
Total |
$4,576,630 |
$1,032,000 |