Legislation Details

File #: DC-6060    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 9/30/2026 In control: Board of Commissioners
On agenda: 10/27/2026 Final action:
Enactment date: Resolution #:
Title: Authorization To Amend 2026 Transportation Capital Improvement Program Budget For Delaware Avenue Improvements In Cities Of West St. Paul And Mendota Heights, County Project 63-33
Sponsors: Transportation
Attachments: 1. Project Location Map
Date Ver.Action ByActionResultAction DetailsMeeting MaterialsVideo
No records to display.

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Amend 2026 Transportation Capital Improvement Program Budget For Delaware Avenue Improvements In Cities Of West St. Paul And Mendota Heights, County Project 63-33

end

 

RESOLUTION

body

WHEREAS, to promote a safe and efficient transportation system, Dakota County is proceeding with County Project (CP) 63-33, County State Aid Highway (CSAH) 63 (Delaware Avenue) reconstruction in the cities of Mendota Heights and West St. Paul; and

 

WHEREAS, CP 63-33 will reconstruct CSAH 63 from Marie Avenue to Trunk Highway 149 (Dodd Road), including roadway modernization, intersection and safety improvements, stormwater facilities, and new, separated pedestrian and bicycle facilities; and

 

WHEREAS, acquisition of easements necessary to construct CP 63-33 has proceeded over the past year, with easements on 74 parcels acquired to date through negotiation or condemnation; and

 

WHEREAS, negotiations for acquisition of easements on one parcel are continuing; and

 

WHEREAS, significant expenses for right of way acquisition remain, including settlements, condemnation hearings, and building demolition; and

 

WHEREAS, a budget amendment to the 2026 Transportation Budget is necessary to complete acquisition of right of way for CP 63-33 and proceed into construction; and

 

WHEREAS, staff recommends increasing the budget of CP 63-33 by $673,714.

 

NOW, THEREFORE, BE IT RESOLVED, That the 2026 Transportation Capital Improvement Program Budget is hereby amended as follows:

 

Expense

County Project 63-33 $673,714

Total Expense $673,714

 

Revenue

County State Aid Highway $572,657

City Local Share $101,057

Total Revenue $673,714

end

 

BACKGROUND

Dakota County is advancing County Project (CP) 63-33 (Attachment: Project Location Map), with construction anticipated to begin in winter 2027 and continuing through fall 2028. Design is substantially complete, and advertisement for construction bids is expected later this year.

 

Acquisition of right of way for CP 63-33 is a significant part of the overall project effort and is nearing completion. Due to the volume of parcels required and the complexity posed by some, Transportation and Real Estate staff elected to seek consultant services for negotiation and acquisition of easements. The County retained Henning Professional Services as a subconsultant to Kimley-Horn and Associates, Inc., the design consultant for the project. The fee for acquisition services totaled $1,021,475. Remaining costs for right of way acquisition total $1,032,000, including settlements on remaining acquisitions, expenses for commissioner viewings and condemnation hearings, and demolition costs on a property purchased in fee. An amendment to the project budget is required to acquire the remaining easements and associated expenses.

 

RECOMMENDATION

recommendation

Staff recommends authorization to amend the 2026 Transportation Budget in the amount of $673,714 to complete right of way acquisitions and related expenses for CP 63-33.

end

 

FINANCIAL AND STAFFING IMPACTS

The 2026 Transportation Capital Improvement Program Budget includes $3,902,916 for CP 63-33 Reconstruction Marie to TH149, with $358,286 of unencumbered funds. The requested amendment would commit $572,657 in County State Aid Highway (CSAH) funding and $101,057 in city funding in accordance with current 2040 Transportation Plan cost share policies. The requested amendment would increase the current approved project budget by $673,714.

 

Current Approved Budget - 1001585 T63033 Reconstruction of Marie to TH149

Funding Source

Total Approved Budget

Available Budget

CSAH Funds

$3,343,533

$304,543

City Funds

$559,383

$53,743

Total

$3,902,916

$358,286

 

Proposed Amended Budget - 1001585 T63033 Reconstruction of Marie to TH149

Funding Source

Total Approved Budget

Available Budget

CSAH Funds

$3,916,190

$877,200

City Funds

$660,440

$154,800

Total

$4,576,630

$1,032,000

 

PREVIOUS BOARD ACTION

26-179; 4/21/26

 

ATTACHMENTS

Attachment: Project Location Map

 

CONTACTS

Department Director: Erin Laberee

Author: Joe Morneau