Title: Authorization To Amend Environmental Legacy Fund Budget To Transfer Fund Balance To Byllesby Dam Enterprise Fund
Sponsors: Finance
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT: Finance

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Amend Environmental Legacy Fund Budget To Transfer Fund Balance To Byllesby Dam Enterprise Fund

end

 

PURPOSE/ACTION REQUESTED

Authorize an amendment to the 2025 budget in the amount of $2,250,000 to permanently transfer funds from the Environmental Legacy Fund (ELF) to Byllesby Dam to cover operating expenses incurred for the Byllesby Dam facility for the period of 2023-2025.

 

SUMMARY

Dakota County owns the Byllesby Dam and operates its high-hazard hydroelectricity facility under the Federal Energy Regulatory Commission (FERC) safety regulations. Over the past several years, the Dakota County Board of Commissioners has approved significant capital investments into this facility. Most recently, the Board approved a turbine upgrade as part of the Byllesby Dam Water-To-Wire Redevelopment Project.

 

Notice to proceed on the Byllesby Dam Water-To-Wire Redevelopment project was given on October 1, 2020. The turbines were taken offline in January 2021. Since that time, Byllesby Dam has not been able to generate electricity. The costs associated with operating and maintaining the facility have been unable to be covered by revenues within the Byllesby Dam Enterprise Fund, leading to a negative fund balance. Due to project delays, a transfer of fund balance in the amount of $2,250,000 from the Environmental Legacy Fund (ELF) is required to cover the operating costs for the period of January 2023 through December 2025 and eliminate the negative fund balance in the Byllesby Dam Enterprise Fund.

 

RECOMMENDATION

recommendation

Staff recommends approval of the proposed budget amendment to the Environmental Legacy Fund and Byllesby Dam Enterprise Fund.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

This amendment will authorize a transfer in the amount of $2,250,000, reducing the Environmental Legacy Fund (ELF) fund balance and increasing the Byllesby Dam Enterprise Fund Balance.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, Dakota County owns and operates the Byllesby Dam, a high-hazard hydroelectricity facility; and

 

WHEREAS, the Dakota County Board of Commissioners approved a turbine upgrade as part of the Byllesby Dam Water-to-Wire Redevelopment Project, leading to a period where the Byllesby Dam has been unable to generate electricity; and

 

WHEREAS, the costs associated with operating and maintaining the facility have been unable to be covered by revenues from electricity generation within the Byllesby Dam Enterprise Fund during the period of January 2023 to December 2025; and

 

WHEREAS, staff recommend a transfer in the amount of $2,250,000 from the Environmental Legacy Fund to the Byllesby Dam Enterprise Fund to cover the operating costs of the Byllesby Dam.

 

NOW, THEREFORE, BE IT RESOLVED, that the Dakota County Board of Commissioners hereby amends the 2025 Budget and approves a transfer of $2,250,000 from the Environmental Legacy to the Byllesby Dam Enterprise Fund; and

 

BE IT FURTHER RESOLVED, That the 2025 Environmental Legacy Fund budget is hereby amended as follows:

 

Revenue

Use of Fund Balance                                                               $2,250,000

Total Revenue                                                                                    $2,250,000

 

Other Financing Use

Transfer to Byllesby Dam                                                               $2,250,000

Total Other Financing Use                                          $2,250,000

; and

 

BE IT FURTHER RESOLVED, That the 2025 Byllesby Dam Enterprise Fund budget is hereby amended as follows:

 

Revenue

Use of Fund Balance                                                                ($2,250,000)

Total Revenue                                                                                    ($2,250,000)

 

Other Financing Source

Transfer from ELF                                                                                     $2,250,000

Total Other Financing Source                                          $2,250,000

                     

end

PREVIOUS BOARD ACTION

None.

 

ATTACHMENTS

None.

 

BOARD GOALS

   Thriving People        A Healthy Environment with Quality Natural Resources

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Will Wallo

Author: Leng Vang