Title: Authorization To Execute Second Contract Amendment With SRF Consulting Group, Inc., For Additional Contract Costs For Trail Construction On Butler Avenue In West St. Paul, County Project 04-17
Sponsors: Transportation
Attachments: 1. Location Map, 2. Amendment No. 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Second Contract Amendment With SRF Consulting Group, Inc., For Additional Contract Costs For Trail Construction On Butler Avenue In West St. Paul, County Project 04-17

end

 

PURPOSE/ACTION REQUESTED

Authorize execution of the second amendment to the contract with SRF Consulting Group, Inc., (SRF) for additional construction administration and inspection services.

 

SUMMARY

To promote a safe and efficient transportation system throughout the County, Dakota County has constructed a trail along Butler Avenue from Robert Street to Trunk Highway (TH) 52 to provide safe pedestrian access to Thompson Park and the surrounding area. A location map is attached. The project began in August 2025 and was substantially complete in December 2025. However, there is still work remaining to be done in 2026 that was not anticipated: specifically, completing the retaining wall on the north side east of Sperl Street. It was determined that building the wall higher would improve the slope behind the wall. This work will be done this spring.

 

The cost of the additional construction administration and inspection amounts to $18,883. This amendment will bring the total contract amount to $271,481, based on an additional two weeks of construction.

 

Summary of attached amendment:                     

                     Construction Administration                                          $  4,120

                     Construction Inspection                                                               $14,400

                     Non-Salary Expenses                                                               $     363

Total                     $18,883

 

The project was awarded to SRF Consulting Group, Inc., on August 12, 2025. The first amendment allowing for additional time due to St. Paul Regional Water Services working in the area and private utility relocations was approved on February 3, 2026.

 

RECOMMENDATION

recommendation

Staff recommends authorizing a contract amendment with SRF Consulting Group, Inc., in the amount of $18,883 for additional costs in construction administration and inspection.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The Transportation Capital Improvement Program included $3.4 million for the construction of the trail, funded by the State Transportation Advancement Account (TAA), wheelage tax, Transportation Fund balance, and cost sharing with the City of West St. Paul. Sufficient funds are available for the recommended contract amendment.

 

Project 04-17 Trail Gap: County Road 4 (Butler Avenue) from TH 952 (Robert Street) to TH 52 in West St. Paul.

 

Funding Source

Total Budget

Available Budget

City of West St. Paul

$420,871

$0

TAA

$700,000

$0

Wheelage Tax

$1,800,000

$380,149

Transportation Fund Balance

$488,820

$488,820

Total

$3,409,691

$868,969

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to promote a safe and efficient transportation system throughout the county, Dakota County has constructed a trail along Butler Avenue from Robert Street to Trunk Highway 52; and

 

WHEREAS, SRF Consulting Group, Inc., was contracted to do construction management and inspection; and

 

WHEREAS, the contract has increased due to work remaining to be done in 2026; and

 

WHEREAS, staff recommends authorizing the execution of an amendment to the contract with SRF Consulting Group, Inc., in the amount of $18,883; and

 

WHEREAS, sufficient funds are available in the 2025 Transportation Capital Improvement Program Adopted Budget for the recommended contract amendment.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Transportation Director to execute a second amendment to the contract with SRF Consulting Group, Inc., in the amount of $18,883 for additional construction management and inspection for County Project 04-17, subject to the approval of the County Attorney’s Office as to form.

end

 

PREVIOUS BOARD ACTION

25-378; 08/12/25

26-065; 02/03/26

 

ATTACHMENTS

Attachment: Location Map

Attachment: Amendment No. 2

 

BOARD GOALS

   Thriving People        A Healthy Environment with Quality Natural Resources

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Erin Laberee

Author: Jeannine Briol