Skip to main content
Dakota County Logo
File #: DC-4779    Version: 1
Type: Consent Action Status: Passed
File created: 7/31/2025 In control: Board of Commissioners
On agenda: 8/26/2025 Final action: 8/26/2025
Enactment date: 8/26/2025 Resolution #: 25-406
Title: Authorization To Amend Contract With Valley Paving, Inc., And Amend 2025 Capital Improvement Program Budget For 2025 Preservation Of Paved Highway Surface Project
Sponsors: Transportation
Attachments: 1. Location Map, 2. Cost Increase Summary

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Amend Contract With Valley Paving, Inc., And Amend 2025 Capital Improvement Program Budget For 2025 Preservation Of Paved Highway Surface Project

end

 

PURPOSE/ACTION REQUESTED

Authorize a contract amendment with Valley Paving, Inc. for additional contract costs on the 2025 Preservation of Paved Highway Surface Project and amend the 2025 Capital Improvement Program (CIP) Budget.

 

SUMMARY

To promote a safe and efficient transportation system, Dakota County proceeded with the 2025 Preservation of Paved Highway Surface Project (Attachment: Location Map). The 2025 preservation work included resurfacing of County roads. The work began in June and will continue through October.

 

By Resolution No. 25-053 (January 21, 2025), the County Board authorized the County Manager or designee to award the Preservation of Paved Highway Surface Project to the lowest responsible bidder. The project was awarded to Valley Paving, Inc., in the amount of $5,576,946.12. Note that the contract amount was 16.5 percent under the Engineer’s estimate.

 

Construction costs have increased by $349,803.44 or 6.3 percent due to a change in the design and higher quantities of pavement resurfacing. A list of item overruns is summarized in Attachment: Cost Increase Summary.

 

On County Project (CP) 11-32, MnDOT requested a change to the design of the pedestrian facility way to meet Americans with Disabilities Act (ADA) requirements for work within their right of way. County staff agreed to the design changes, which increased costs by an additional $225,823.13.

 

On County Project (CP) 91-34, there was an increase in milling and pavement quantities.  The increased project cost due to the increase in quantities is $123,980.31.

 

RECOMMENDATION

recommendation

Staff recommends authorizing a contract amendment in the amount of $349,803.44 for a revised contract amount of $5,926,749.56 and a budget amendment in the amount of $349,803.44.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The 2025 CIP has a total adopted budget of $8,200,000 for the Preservation of Paved Highway Surface Project. A budget amendment in the amount of $349,803.44 is requested for the increased construction cost and design change. The budget amendment will use remaining dollars in the 2025 CIP budget for Preservation of Paved Highway Surface and allocate it to the specific projects.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to promote a safe and efficient transportation system, Dakota County proceeded with the 2025 Preservation of Paved Highway Surface project; and

 

WHEREAS, the 2025 preservation work included resurfacing of county roads; and

 

WHEREAS, the work began in June 2025 and will continue through October 2025; and

 

WHEREAS, by Resolution No. 25-053 (January 21, 2025), the project was awarded to Valley Paving, Inc., in the amount of $5,576,946.12; and

 

WHEREAS, construction costs have increased by $349,803.44 or 6.3 percent due to a design change and higher quantities of pavement resurfacing; and

 

WHEREAS, staff recommends authorizing a contract amendment in the amount of $349,803.44 for a revised contract amount of $5,926,749.56, and a budget amendment of $349,803.44.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby approves the contract amendment and authorizes the Physical Development Director to execute a contract amendment with Valley Paving, Inc., for the 2025 Preservation of Paved Highway Surface project, in the amount of $349,803.44, subject to approval by the County Attorney’s Office as to form; and

 

BE IT FURTHER RESOLVED, That the 2025 Capital Improvement Program Adopted Budget is hereby amended as follows:

 

                     Revenue

                     CP 11-32 - TAA                     $225,824

                     CP 91-34 - TAA                       $123,981                     

                     2025 Paved Highway Surface - TAA                     ($349,805)

                     Total Revenue                     $0

 

                     Expense

                     CP 11-32                     $225,824

                     CP 91-34                       $123,981                     

                     2025 Paved Highway Surface Set-aside                     ($349,805)

                     Total Expense                     $0

 

end

PREVIOUS BOARD ACTION

25-053; 1/21/25

 

ATTACHMENTS

Attachment: Project Location Map

Attachment: Cost Increase Summary

 

BOARD GOALS

   Thriving People        A Healthy Environment with Quality Natural Resources

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Erin Laberee

Author: Kevin Krech