Skip to main content
Dakota County Logo
File #: DC-1546    Version: 1
Type: Consent Action Status: Passed
File created: 10/18/2022 In control: Board of Commissioners
On agenda: 12/13/2022 Final action: 12/13/2022
Enactment date: 12/13/2022 Resolution #: 22-556
Title: Authorization To Amend Transportation Capital Improvement Program Budget For County Project 8-21, Wentworth Avenue (CSAH 8) Reconstruction From Delaware Avenue (CSAH 63) To Humboldt Avenue In City Of West St. Paul
Sponsors: Transportation
Attachments: 1. Financial Summary

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Amend Transportation Capital Improvement Program Budget For County Project 8-21, Wentworth Avenue (CSAH 8) Reconstruction From Delaware Avenue (CSAH 63) To Humboldt Avenue In City Of West St. Paul

end

 

PURPOSE/ACTION REQUESTED

Authorize to amend the 2022 Transportation Capital Improvement Program (CIP) for County Project (CP) 8-21 in the City of West St. Paul.

 

SUMMARY

To provide a safe and efficient transportation system, Dakota County, in cooperation with the City, reconstructed County State Aid Highway (CSAH) 8 from CSAH 63 (Delaware Avenue) to Humboldt Avenue. The project included the reconstruction of the roadway, drainage improvements, and the installation of pedestrian accommodations. The project was constructed in 2019, with some minor work completed in the Spring of 2020.

 

The Construction contract with S.M. Hentges and Sons, Inc., was awarded in the amount of $5,388,701, and the final contract amount was $5,368,667. A contract dispute in the amount of $650,000 remained unresolved until the Attorney’s Office prevailed in a jury trial in May of 2022. Additional project costs were incurred, including attorney’s office charges, expert witness reports and testimony, and legal document costs. These costs total $120,000 above the adopted budget for the project.

 

In addition, there is one parcel acquisition remaining at an estimated cost of $40,000.

 

A budget amendment is requested to account for this difference. The City of West St. Paul’s share of project costs is capped at 25 percent.

 

RECOMMENDATION

recommendation

Staff recommends amending the 2022 Transportation CIP Adopted Budget for CP 8-21 to account for additional legal costs and right of way acquisition costs.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The total adopted budget for CP 8-21 is $6,757,942. To account for additional legal costs and right of way costs, a budget amendment of $160,000 is requested for a final project budget of $6,917,942 (see Attachment: Financial Summary). The requested budget amendment would involve transferring funds from the Transportation Fund Balance.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, Dakota County and the City of West St. Paul are partnered on County Project (CP) 8-21 to reconstruct County State Aid Highway (CSAH) 8 in West St. Paul; and

 

WHEREAS, the construction contract was awarded to S.M. Hentges & Sons, Inc., in the amount of $5,388,701, and the final contract amount was $5,368,667; and

 

WHEREAS, a legal dispute resulted in additional project costs totaling $120,000; and

 

WHEREAS, one parcel remains to be acquired at an additional remaining cost of $40,000; and

 

WHEREAS, a budget amendment is requested to account for the remaining legal and right of way acquisition costs; and

 

WHEREAS, staff recommends amending the 2022 Transportation Capital Improvement Program Adopted Budget for CP 8-21 to account for additional legal costs and right of way acquisition costs.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby amends the 2022 Transportation Capital Improvement Program Adopted budget as follows:

 

                     Expense

                     County Project 8-21                                                               $160,000

                     Total Expense                                                               $160,000

 

                     Revenue

                     City of West St. Paul                                          $  40,000

                     Transportation Fund Balance                     $120,000

                     Total Revenue                                                               $160,000

end

 

PREVIOUS BOARD ACTION

None.

 

ATTACHMENTS

Attachment: Financial Summary

 

BOARD GOALS

   A Great Place to Live                                          A Healthy Environment     

   A Successful Place for Business and Jobs         Excellence in Public Service

 

PUBLIC ENGAGEMENT LEVEL

  Inform and Listen                Discuss                               Involve                               N/A

 

CONTACT

Department Head: Erin Laberee

Author: Todd Howard