Legislation Details

File #: DC-3067    Version: 2
Type: Consent Action Status: Passed
File created: 1/29/2024 In control: Board of Commissioners
On agenda: 3/12/2024 Final action: 3/12/2024
Enactment date: 3/12/2024 Resolution #: 24-129
Title: Authorization To Enter Into A Joint Powers Agreement With City Of Eagan, Award Bid, And Execute Construction Contract With McNamara Contracting, Inc. For Intersection Improvements Along County State Aid Highway 28 In City Of Eagan, County Project 28-44
Sponsors: Transportation
Attachments: 1. Project Location Map, 2. Financial Summary

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Enter Into A Joint Powers Agreement With City Of Eagan, Award Bid, And Execute Construction Contract With McNamara Contracting, Inc. For Intersection Improvements Along County State Aid Highway 28 In City Of Eagan, County Project 28-44

end

 

PURPOSE/ACTION REQUESTED

•                     Authorize entering into a joint powers agreement (JPA) with the City of Eagan to establish roles, responsibilities, and cost share for the intersection improvements project along County State Aid Highway (CSAH) 28, County Project (CP) 28-44.

•                     Award bid and authorize a construction contract with McNamara Contracting, Inc., for intersection improvements along CSAH 28, CP 28-44.

 

SUMMARY

To promote a safe and efficient transportation system, Dakota County and the City of Eagan are partnering on County Project (CP) 28-44, which consists of intersection improvements along CSAH 28 (Yankee Doddle Road) at Mike Collins Dr./Ivy Lane and Elrene Road (Attachment: Project Location Map). The proposed improvements are anticipated to include the construction of restricted access Mike Collins Drive/Ivy Lane and the installation of a new traffic signal at Elrene Road based on previous studies, pedestrian ramp improvements at both intersections and the addition of a new right-turn lane at Wescott Square. A mill and overlay are also planned in the project area along CSAH 28 to address striping configuration changes from the updates to the median geometry and to improve pavement quality. The purpose of the project is to improve safety, operations and incorporate recommendations from previous corridor studies.

 

A JPA between the County and the City of Eagan is necessary to outline cost participation, preliminary and final design responsibilities, future maintenance responsibility, and construction for CP 28-44. Costs will be shared in accordance with County policy. The County is the lead agency for design, right of way acquisition, and construction phases. 

 

Construction is planned to start in spring of 2024 and be substantially complete by November 2024. Construction bids were received and tabulated on February 13, 2024. Seven bidders submitted bids as follows:

 

Bidder                                                                                                                                                   Bid Amount                                          

 

McNamara Contracting, Inc.                                                               $1,760,354.90

OMG Midwest Inc.                                                                                                         $1,889,442.61

Park Construction Company                                                               $1,892,922.09

S M Hentges & Sons Inc.                                                                                    $1,961,692.65

Valley Paving, Inc.                                                                                                         $2,116,755.35

Pember Companies, Inc.                                                                                    $2,190,586.65

Bituminous Roadways, Inc.                                                                         $2,190,586.65

 

The engineers estimate for this project is $2,159,386.00 and staff has determined the bids to be responsive and competitive. The lowest responsive and responsible bid for CP 28-44 is $1,760,354.90 from McNamara Contracting, Inc., which is 18.5 percent under the engineer’s estimate of $2,159,386.00. Staff have reviewed the bids and determined that the bid was competitive at the time of bidding. This is a non-federal project using State Aid and County funds. No approvals from MnDOT are needed for award.

 

RECOMMENDATION

recommendation

Staff recommends authorization to enter a JPA with the City of Eagan to formalize cost contributions and responsibilities for design and construction of CP 28-44.

 

Staff also recommends awarding the bid to and authorizing execution of a contract with McNamara Contracting, Inc., in the amount of $1,760,354.90.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The 2024 Transportation Capital Improvement Program (CIP) Adopted Budget includes a total project budget of $2,690,014 which include carryovers from previous CIP budgets. Costs for design and construction will be split between County and City of Eagan in accordance with the Cost Share Policy as outlined in the Dakota County 2040 Transportation Plan (July 2021). Actual cost splits will be determined based on construction costs. Sufficient funds are available to award the construction contract.

 

  ☐ None              ☒ Current budget              ☐ Other        

  ☐ Amendment Requested                           ☐ New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to provide a safe and efficient transportation system, Dakota County and the City of Eagan (City) are proceeding with County Project (CP) 28-44; and

 

WHEREAS, the County is the lead agency for the Project that includes intersection improvements along County State Aid Highway (CSAH) 28 (Yankee Doodle Road) In City of Eagan and addition of a right turn lane at Wescott Square; and

 

WHEREAS, the purpose of the project is to improve safety, operations, and pavement quality; and

 

WHEREAS, construction is scheduled to begin in spring of 2024; and

 

WHEREAS, a joint powers agreement (JPA) between the County and the City of Eagan is necessary to outline cost participation, preliminary and final design responsibilities, future maintenance responsibility, and construction for CP 28-44; and

 

WHEREAS, the cost participation for the Project outlined in the JPA will be in accordance with the adopted Cost Share Policy; and

 

WHEREAS, the 2024 Transportation Capital Improvement Program (CIP) Adopted Budget includes a total budget of $2,690,014 for CP 28-44 project design, right of way acquisition, and construction; and

 

WHEREAS, pursuant to advertisement, seven bids were received for CP 28-44 on February 13, 2024; and

 

WHEREAS, the bid of McNamara Contracting, Inc., in the amount of $1,760,354.90 was the lowest responsive and responsible bid received; and

 

WHEREAS, the 2024 Transportation Capital Improvement Program (CIP) Adopted Budget includes sufficient funds for the Project; and

 

WHEREAS, staff recommends awarding the bid to McNamara Contracting, Inc.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Physical Development Director to enter a joint powers agreement between Dakota County and the City of Eagan for the design and construction of County Project 28-44; and

 

BE IT FURTHER RESOLVED, That the Dakota County Board of Commissioners hereby awards the bid to and authorizes the Physical Development Director to execute the contract with McNamara Contracting, Inc. for County Project 28-44 in the amount of $1,760,354.90 based on their low bid, subject to approval by the County Attorney’s Office as to form.

end

 

PREVIOUS BOARD ACTION

23-137; 3/28/23

 

ATTACHMENTS

Attachment: Project Location Map

Attachment: Financial Summary

 

BOARD GOALS

   ☒ A Great Place to Live                                          ☐ A Healthy Environment     

   ☐ A Successful Place for Business and Jobs         ☐ Excellence in Public Service

 

CONTACT

Department Head: Erin Laberee

Author: Hassan Hussein