Dakota County Logo
File #: DC-3470    Version: 1
Type: Consent Action Status: Passed
File created: 5/20/2024 In control: Board of Commissioners
On agenda: 7/9/2024 Final action: 7/9/2024
Enactment date: 7/9/2024 Resolution #: 24-350
Title: Authorization To Award And Execute Contract With New Look Contracting, Inc. For Signal Reconstruction At Pilot Knob Road And Corporate Center Drive In City Of Eagan, County Project 31-103
Sponsors: Transportation
Attachments: 1. Location Map

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Award And Execute Contract With New Look Contracting, Inc. For Signal Reconstruction At Pilot Knob Road And Corporate Center Drive In City Of Eagan, County Project 31-103

end

 

PURPOSE/ACTION REQUESTED

Award bid and authorize execution of a contract with New Look Contracting, Inc. for County Project (CP) 31-103 in the City of Eagan.

 

SUMMARY

To promote a safe and efficient transportation system, Dakota County and the City of Eagan are partnering on CP 31-103. The signal reconstruction will occur at County State Aid Highway (CSAH) 31 (Pilot Knob Road) and Corporate Center Drive (Attachment: Location Map).

 

County Project 31-103 will replace the aging signal system, construct additional turn lanes, and install Americans with Disabilities Act (ADA) compliant ramps, lighting, curb and gutter, sidewalks/trails, and storm sewer at the intersection of CSAH 31 and Corporate Center Drive.

 

The County is the lead agency for the project with construction anticipated to begin in summer 2024.

 

By Resolution No. 23-075 (February 28th, 2023), the County Board authorized the execution of a joint powers agreement (JPA) with the City of Eagan to define costs and responsibilities for CP 31-103.

 

The County issued the project advertisement, and five responsive bids were received and tabulated for CP 31-103 on Friday, June 21st, 2024.

 

Bidder

Total Amount

New Look Contracting, Inc.

$1,315,829.75

McNamara Contracting, Inc.

$1,329,973.00

Park Construction Company

$1,368,700.93

Meyer Contracting Inc.

$1,406,729.98

Urban Companies

$1,560,995.68

 

The engineer’s estimate for CP 31-103 is $974,678. Staff reviewed the bids, and the lowest responsible bid is $1,315,829.75 from New Look Contracting, Inc., which is 35 percent above the estimate. Signal system, signing and striping, and grading were the largest work categories contributing to the discrepancy from estimated to bid cost. The current bidding climate as well as small quantities for several items are believed to have influenced the bid cost, as the costs were largely consistent across the contractors. Staff has reviewed the bids and determined the bids competitive.

The County and City will be responsible for the local share at a cost split of 85 percent County and 15 percent City for the turn lane installation and 50 percent County and 50 percent City for signal installation in accordance with the 2040 Dakota County Transportation Plan Cost Policy F.1 per the executed JPA.

 

RECOMMENDATION

recommendation

Staff recommends awarding the bid to New Look Contracting, Inc.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The 2024 Transportation Capital Improvement Program Adopted Budget contains a total budget of $937,833, with $822,521 remaining for CP 31-103. An additional amount of $493,308.75 will be needed and has been requested from the 2024 Transportation Capital Improvement Program Traffic Signal - New/Replacement set-aside to CP 31-103 through an administrative amendment. The referenced set-aside has sufficient funds to accommodate this transfer. 

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to promote a safe and efficient transportation system, Dakota County and the City of Eagan are partnering on County Project (CP) 31-103; and

 

WHEREAS, the project will occur at County State Aid Highway (CSAH) 31 (Pilot Knob Road) and Corporate Center Drive; and

 

WHEREAS, CP 31-103 will replace the aging signal system, construction of additional turn lanes, and install Americans with Disabilities Act (ADA) compliant ramps, lighting, curb and gutter, sidewalks/trails, and storm sewer at the intersection of CSAH 31 and Corporate Center Drive; and

 

WHEREAS, the County is the lead agency for CP 31-103, with construction anticipated to begin in summer 2024; and

 

WHEREAS, the County and City will be responsible for the local share at a cost split of 85 percent County and 15 percent City for the turn lane installation and 50 percent County and 50 percent City for signal installation in accordance with the 2040 Dakota County Transportation Plan Cost Policy F.1, per the executed joint powers agreement (JPA); and

 

WHEREAS, the project was advertised, and five bids were received and tabulated on Friday, June 21, 2024; and

 

WHEREAS, the bid from New Look Contracting, Inc. in the amount of $1,315,829.75 was the lowest responsible bid received; and

 

WHEREAS, staff recommends awarding the bid to New Look Contracting, Inc.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby awards the bid to and authorizes the Physical Development Director to execute the contract with New Look Contracting, Inc. for County Project 31-103, in the amount of $1,315,829.75 based on their low bid, subject to approval by the County Attorney’s Office as to form.

end

 

PREVIOUS BOARD ACTION

23-075; 2/28/23

 

ATTACHMENTS

Attachment: Location Map

 

BOARD GOALS

   A Great Place to Live                                          A Healthy Environment     

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Erin Laberee

Author: Tyler Krage