Legislation Details

File #: DC-4277    Version: 1
Type: Consent Action Status: Passed
File created: 2/11/2025 In control: Board of Commissioners
On agenda: 3/25/2025 Final action: 3/25/2025
Enactment date: 3/25/2025 Resolution #: 25-163
Title: Authorization To Execute Contract With WSB LLC, For Design Services For Federal Mill And Overlay On County State Aid Highway (CSAH) 42 (150th Street W), County Project (CP) 42-173, And WSP USA Inc. For Design Services For Federal Mill And Overlay On CSAH 23 (Cedar Ave), CP 23-088 And Amend 2025 Transportation Capital Improvement Program Budget For CP 42-173 And CP 23-088
Sponsors: Transportation
Attachments: 1. Location Map CP 42-173, 2. Location Map CP 23-088

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Contract With WSB LLC, For Design Services For Federal Mill And Overlay On County State Aid Highway (CSAH) 42 (150th Street W), County Project (CP) 42-173, And WSP USA Inc. For Design Services For Federal Mill And Overlay On CSAH 23 (Cedar Ave), CP 23-088 And Amend 2025 Transportation Capital Improvement Program Budget For CP 42-173 And CP 23-088

end

 

PURPOSE/ACTION REQUESTED

•                     Authorize the execution of a contract with WSB LLC for design consulting services for County Project (CP) 42-173, federal mill and overlay on County State Aid Highway (CSAH) 42 in Apple Valley and Rosemount (Attachment: Location Map).

•                     Authorize the execution of a contract with WSP USA Inc. for design consulting services for CP 23-088, federal mill and overlay on CSAH 23 in Apple Valley and Lakeville (Attachment: Location Map).

•                     Authorize an amendment of the 2025 Transportation Capital Improvement Program (CIP) Budget for CP 42-173 and CP 23-088

 

SUMMARY

Project Background

To provide a safe and efficient transportation system, the County is planning two federal mill and overlay preservation projects for four-lane divided principal arterial routes. County Project 42-173 involves County State Aid Highway CSAH 42 (150th Street W) from CSAH 33 (Diamond Path) to Trunk Highway 3 (Robert Trail S) in Apple Valley and Rosemount. County Project 23-088 includes CSAH 23 (Cedar Ave) from CSAH 9 (179th Street) to CSAH 42 (150th Street W) in Apple Valley and Lakeville.

 

These preservation projects will include the following:

•                     Pavement milling and overlay

•                     Replacement of pedestrian curb ramps at intersections to comply with the Americans with Disabilities Act (ADA)

•                     Application of pavement markings

•                     Necessary repairs to city utilities

 

As part of pavement preservation efforts, the County collaborates with municipal partners to assess any utility improvements needed on the road segments being enhanced. Including these improvements in the preservation work saves stakeholders time and money, minimizing traffic disruptions by consolidating impacts into a single project instead of multiple ones. Potential improvements often include repairs to storm sewer, sanitary sewer, and water main facilities.

 

Both CSAH 23 and CSAH 42 serve communities, residents, businesses, commuters, freight, transit, and multi-modal transportation users in the area. Pavement along both corridors has reached the end of its useful life. The corridors’ pavement has severe cracking, failing curb, and non-compliant pedestrian facilities, and other systems with non-compliant Accessible Pedestrian Signals (APS) will be improved at all signalized intersections.

 

CP 23-088 and CP 42-173 will partially utilize National Highway System federal funds to achieve the necessary pavement improvements and ADA pedestrian improvements.

 

Scope of Work

The scope of work for CP 42-172 and CP 23-088 includes public involvement and agency coordination, corridor evaluation, data collection, permits, approvals, surveys, traffic analysis, and roadway preliminary design, as well as final design of pavement improvements, pedestrian crossing enhancements, and signal systems. The completed product will provide a safe transportation system and ADA compliance for the County Highway System within the Cities of Apple Valley, Rosemount and Lakeville.

 

Consultant Selection and Roles

Dakota County issued a Request for Proposal (RFP) for the above-noted services on January 24, 2025 for CP 42-173 and CP 23-088. Five proposals were received for both the projects on February 14, 2025, and evaluated by staff representing the County and the Cities of Apple Valley, Lakeville, and Rosemount. The preferred professional engineering consultants were selected based on the following criteria: project understanding, project approach, public involvement, team expertise, quality control, performance on similar projects, and best-value cost.

 

WSP USA Inc. is the preferred professional engineering consultant for CP 23-088. The consultants submitted cost proposals as follows for CP 23-088:

 

Consultant                                                       Total Cost                     Hours                       Cost Per Hour

Stonebrooke Engineering                     $508,350                     3404                       $149

WSB LLC                                                                         $303,167                     1734                       $175

Alliant Engineering                                          $435,455                     2968                       $147

Bolton & Menk, Inc.                                          $504,974                     3159                       $160

WSP USA Inc.                                          $371,589                     2402                       $155

 

WSB LLC is the preferred professional engineering consultant for CP 42-173. The consultants submitted cost proposals as follows for CP 42-173:

 

Consultant                                                       Total Cost                     Hours                       Cost Per Hour

Stonebrooke Engineering                     $356,350                     2340                       $152

WSB LLC                                                                         $277,955                     1559                       $178

Alliant Engineering                                          $319,935                     2213                       $145

Bolton & Menk, Inc.                                          $310,656                     1912                       $163

WSP USA Inc.                                          $364,845                     2350                       $155

  

The proposals were evaluated to determine whether the work plan, hours, and rate structure were sufficient and reasonable to successfully complete the final design and related work. The proposals from WSB LLC and WSP USA Inc. provided the most responsive and complete work plan, which best addressed the issues and requested scope laid out in the RFP.

 

An amendment to the approved 2025 CIP budget is necessary. The 2025 Transportation CIP Approved Budget does not have sufficient funds for the professional engineering services for CP 42-173 and CP 23-088. The consulting services budget shortage for CP 42-173 is $2,955 and the consulting services budget shortage for CP 23-088 is $46,589. The budget shortage is being funded by the CSAH funds.

 

RECOMMENDATION

recommendation

Staff recommends execution of a contract with WSP USA Inc. for professional design services for projects CP 23-088 not to exceed $371,589 and execute a contract with WSB LLC for CP 42-173 not to exceed $277,955 and amendment of the 2025 Transportation CIP Adopted Budget.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The adopted 2025 Transportation Capital Improvement Program Budget includes $275,000 for CP 42-173 and $325,000 for CP 23-088 for consulting services. There is a budget shortage of $2,955 for CP 42-173, and there is a budget shortage of $46,589 for CP 23-088 for consulting services. An additional $50,000 is being requested for each project to cover title orders, permit fees, printing charges, attorney fees, and documentation. A budget amendment of $52,955 is needed for CP 42-173, and a budget amendment of $96,589 is needed for CP 23-088. The funding shortages are being funded by CSAH funds.

 

  ☐ None              ☐ Current budget              ☐ Other        

  ☒ Amendment Requested                           ☐ New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to provide a safe and efficient transportation system, Dakota County is proceeding with County Project (CP) 23-088 and CP 42-173; and

 

WHEREAS, CP 23-088 is the federal mill and overlay on County State Aid Highway (CSAH) 23 in Apple Valley and Lakeville; and

 

WHEREAS, CP 42-173 is the federal mill and overlay on CSAH 42 in Apple Valley and Rosemount; and

 

WHEREAS, County staff sent a Request for Proposals to five qualified professional consultants; and

 

WHEREAS, the proposals received were evaluated by County staff; and

 

WHEREAS, the proposal from WSB LLC for CP 42-173 has the most complete project scope and best value costs for the Project and provides all the services needed; and

 

WHEREAS, the proposal from WSP USA Inc. for CP 23-088 has the most complete project scope and best value costs for the Project and provides all the services needed; and

 

WHEREAS, the adopted 2025 Transportation Capital Improvement Program Budget includes $275,000 for CP 42-173 for engineering consulting services; and

 

WHEREAS, the adopted 2025 Transportation Capital Improvement Program Budget includes $325,000 for CP 23-088 for engineering consulting services; and

 

WHEREAS, the cost share for the 2025 budget year for each project is 100 percent County funds.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Department Director to execute a contract with WSP USA Inc., to perform consulting design services for County Project 23-088 in an amount not to exceed $371,589, subject to approval by the County Attorney’s Office as to form.

 

BE IT FURTHER RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Department Director to execute a contract with WSB LLC to perform consulting design services for County Project 42-173 in an amount not to exceed $277,955, subject to approval by the County Attorney’s Office as to form.

 

BE IT FURTHER RESOLVED, That the 2025 Transportation Capital Improvement Program Adopted Budget is hereby amended as follows:

 

                     Expense - CP 42-173

                     Consulting Services, CP 42-173                     $2,955

                     Additional Expenses, CP 42-173                     $50,000

                     Total Expense - CP 42-173                     $52,995

 

                     Revenue

                     CSAH Fund Balance, CP 42-173                     $52,995

                     Total Revenue                     $52,995

                     

                     Expense - CP 42-173

                     Consulting Services, CP 23-088                     $46,589

                     Additional Expenses, CP 23-088                     $50,000

                     Total Expense - CP 23-088                     $96,589

 

                     Revenue

                     CSAH Fund Balance, CP 23-088                     $96,589

                     Total Revenue                     $96,589

end

 

PREVIOUS BOARD ACTION

None

 

ATTACHMENTS

Attachment: Location Map CP 42-173

Attachment: Location Map CP 23-088

 

BOARD GOALS

   ☐ Thriving People        ☐ A Healthy Environment with Quality Natural Resources

   ☒ A Successful Place for Business and Jobs         ☐ Excellence in Public Service

 

CONTACT

Department Head: Erin Laberee

Author: Saeed Kanwar