File #: DC-5254    Version: 1
Type: Consent Action Status: Passed
File created: 1/6/2026 In control: Board of Commissioners
On agenda: 2/17/2026 Final action: 2/17/2026
Enactment date: 2/17/2026 Resolution #: 26-080
Title: Authorization To Approve Contract Amendment With Park Construction Company And Amend 2026 Transportation Capital Improvement Plan Budget For County State Aid Highway 26 (Lone Oak Road) Roadway Improvements In City Of Eagan, County Project 26-67
Sponsors: Transportation
Indexes: Yes
Attachments: 1. Location Map, 2. Cost Increase Summary 26-67

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Approve Contract Amendment With Park Construction Company And Amend 2026 Transportation Capital Improvement Plan Budget For County State Aid Highway 26 (Lone Oak Road) Roadway Improvements In City Of Eagan, County Project 26-67

end

 

PURPOSE/ACTION REQUESTED

                     Authorize a contract amendment with Park Construction Company for additional contract costs on County Project (CP) 26-67.

                     Authorize the amendment of the adopted 2026 Transportation Capital Improvement Program (CIP) Budget.

 

SUMMARY

To provide a safe and efficient transportation system Dakota County proceeded with CP 26-67 in the City of Eagan. County Project 26-67 included improvements to County State Aid Highway (CSAH) 26 (Lone Oak Road) from Trunk Highway (TH) 13 to I-35E in Eagan (Attachment: Location Map). The corridor segment between TH 13 and CSAH 31 (Pilot Knob Road) included a multi-use trail as part of the School Area Safety Assessment recommendations for Pilot Knob STEM School and a roadway lane reduction from four to three lanes for the segment from CSAH 31 to I-35E. Construction began in April 2025 and is essentially complete with only minor items remaining.

 

The County Board Awarded CP 26-67 to Park Construction Company by Resolution No. 25-106 on February 18, 2025, in the amount of $7,033,172.20. Note the Engineer’s estimate for the reconstruction was $8,271,430, nearly $1.25 million over the low bid.

 

Construction costs have increased by $498,165 or 7.1 percent due primarily to increased retaining wall costs. Poor soils were discovered during construction of the retaining wall requiring additional excavation and a larger wall. Watermain relocation was also required as part of the redesigned wall. Increased costs are summarized as follows:

 

                     Item                     Amount

                     Redesigned wall                     $382,200

                     Additional watermain work                     $ 54,200

                     Bituminous quantity overrun                     $ 70,000

                     Other quantity overruns and underruns                     $ (8,235)

                     Total                     $ 498,165

 

A more detailed list of Contract changes is summarized in Attachment: Cost Increase Summary.

 

RECOMMENDATION

recommendation

Staff recommends authorizing a contract amendment with Park Construction Company in the amount of $498,165 for a revised contract amount of $7,531,337.20. A budget amendment is also recommended from the 2026 Transportation Capital Improvement Program Budget.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The Transportation Capital Improvement Program Budget has a budget for CP 26-67 of $9,180,000 for consulting services, land acquisition, and construction costs. Funds have been fully utilized and a budget amendment in the amount of $498,165 is requested for the additional construction contract costs.

 

An amendment to the project budget is necessary to account for the $498,165 of increased construction costs. The City of Eagan is responsible for approximately $18,000 of the increase. The amended budget for CP 26-67 will be $9,678,165 if the amendment is approved.

 

Current Budget

CP 26-67 CSAH 26 (Lone Oak Road) from Trunk Highway 13 to I-35E

Funding Source

Total Budget

Available Budget

CSAH

$3,357,500

$0

City of Eagan

$672,500

$0

Federal

$4,740,000

$0

Transportation Fund Balance

$410,000

$50,425

Total

$9,180,000

$50,425

 

Budget - After Proposed Amendment

CP 26-67 CSAH 26 (Lone Oak Road) from Trunk Highway 13 to I-35E

Funding Source

Total Budget

Available Budget

CSAH

$3,357,500

$480,165

City of Eagan

$690,500

$18,000

Federal

$4,740,000

$0

Transportation Fund Balance

$890,165

$50,425

Total

$9,678,165

$548,590

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to provide a safe and efficient transportation system, Dakota County (County) proceeded with County Project (CP) 26-67, the reconstruction of County State Aid Highway (CSAH) 26 from Trunk Highway (TH) 13 to CSAH 31 and a lane reduction of CSAH 26 from CSAH 31 to I-35E in the City of Eagan; and

 

WHEREAS, CP 26-67 includes a trail as part of the School Area Safety Assessment recommendations for Pilot Knob STEM School from TH 13 to CSAH 31; and

 

WHEREAS, the County Board awarded CP 26-67 to Park Construction Company by Resolution No. 25-106 (February 18, 2025), in the amount of $7,033,172; and

 

WHEREAS, construction costs have increased by $498,165 or 7.1 percent due primarily to increased retaining wall costs; and

 

WHEREAS, increased costs are summarized as follows:

 

                     Item                     Amount

                     Redesigned wall                     $382,200

                     Additional watermain work                     $ 54,200

                     Bituminous quantity overrun                     $ 70,000

                     Other quantity overruns and underruns                     $ (8,235)

                     Total                     $ 498,165

; and

 

WHEREAS, staff recommends authorizing a contract amendment with Park Construction Company in the amount of $498,165 for a revised contract amount of $7,531,337.20; and

 

WHEREAS, staff recommends a budget amendment to the 2026 adopted Transportation Capital Improvement Program Budget to account for the increased costs.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby approves the Contract Amendment and authorizes the Transportation Director to execute a contract amendment with Park Construction Company for the construction of County Project 26-67 in an amount of $498,165.00, resulting in a total amended contract not to exceed $7,531,337.20, subject to approval by the County Attorney’s Office as to form; and

 

BE IT FURTHER RESOLVED, That the adopted 2026 Transportation Capital Improvement Program Budget is hereby amended as follows:

 

Expense

County Project 26-67                $498,165

Total Expense                         $498,165

 

Revenue

State Aid                                  $480,165

City of Eagan                           $  18,000

Total Revenue                        $498,165