File #: DC-1612    Version: 1
Type: Consent Action Status: Passed
File created: 11/7/2022 In control: Board of Commissioners
On agenda: 12/13/2022 Final action: 12/13/2022
Enactment date: 12/13/2022 Resolution #: 22-561
Title: Authorization To Award Bid And Execute Contract With Kraft Mechanical, LLC. To Provide General Contractor Services For Law Enforcement Center Water Heater Replacements Project And Authorization To Amend 2022 Buildings Capital Improvement Program
Sponsors: Parks, Facilities, and Fleet Management
Attachments: 1. Financial Summary

DEPARTMENT: Parks, Facilities, and Fleet Management

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Award Bid And Execute Contract With Kraft Mechanical, LLC. To Provide General Contractor Services For Law Enforcement Center Water Heater Replacements Project And Authorization To Amend 2022 Buildings Capital Improvement Program

end

 

PURPOSE/ACTION REQUESTED

Authorize award and execution of a contract with Kraft Mechanical, LLC. to provide general contractor services for the Law Enforcement Center (LEC) Water Heater Replacements project.

Authorize a budget amendment to the 2022 Buildings Capital Improvement Program (CIP) to support increased scope.

 

SUMMARY

The original water heaters were installed in 2007 and have reached the end of their useful life. These water heaters not only provide direct domestic water for the showers in the jail but also supply all the hot water to the laundry equipment.

 

This project is included on the list of projects that were approved by the County Board by Resolution No. 22-101 (March 8, 2022), to authorize award of design and construction to accomplish 2022 Buildings Capital Improvement projects. However, the scope of the project changed from the simple one-for-one replacement of the two existing water heaters to adding water storage which should increase the life of this critical system. The additional piping and water storage increase the construction cost, and a budget amendment is necessary for this project.

 

Base Bid A includes quantity three 400 MBH water heaters with water storage. Base Bid B includes quantity two 800 MBH water heaters with water storage.

 

A public bid was advertised on October 28, 2022. Three bids were received and opened on November 22, 2022. The bids received are as follows:

 

                     Bidder                                                                                                         Base Bid A Amount                                           Base Bid B Amount

                     Kraft Mechanical, LLC.                                          $277,000                                                               $365,000

                     Modern Piping                                                               $279,900                                                               $357,300

                     Morcon Construction                                          $352,074                                                               $420,745

 

Staff and Wold Architects and Engineers, the project design firm, recommend Base Bid A as the best value.

 

Staff and Wold Architects and Engineers, the project design firm, reviewed the bidder qualifications and found that Kraft Mechanical, LLC. has submitted the lowest responsive and responsible bid.

 

RECOMMENDATION

recommendation

Staff recommends the Base Bid A for the LEC Water Heater Replacement project be awarded to Kraft Mechanical, LLC. in an amount not to exceed $277,000.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The 2022 Building CIP Adopted Budget for the Project includes a total project budget of $100,000 (see Attachment: Financial Summary). A budget amendment is needed to move funding from the Prior Project Savings project to the LEC Water Heater Replacements project in order to account for the increased scope and construction costs of the water heaters replacement.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, the 2022 Building Capital Improvement Program (CIP) Adopted Budget authorized the Law Enforcement Center (LEC) Water Heater Replacements project; and

 

WHEREAS, bid documents and specifications were prepared by Wold Architects and Engineers and advertised on October 28, 2022; and

 

WHEREAS, three competitive bids were received on November 22, 2022; and

 

WHEREAS, Kraft Mechanical, LLC. has submitted a bid of $277,000 for Base Bid A; and

 

WHEREAS, staff and Wold Architects and Engineers reviewed the qualifications of the bidder and recommend award to Kraft Mechanical, LLC. as the lowest responsive and responsible bidder, in an amount not to exceed $277,000, for the LEC Water Heater Replacements project; and

 

WHEREAS, funding for the project is within the amended 2022 Building CIP Adopted Budget.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Parks, Facilities, and Fleet Management Director to execute a contract with Kraft Mechanical, LLC., 2415 Ventura Drive, Suite 100, Woodbury MN 55125 in an amount not to exceed $277,000, for the Law Enforcement Center Water Heater Replacements project, subject to approval by the County Attorney’s office as to form; and

 

BE IT FURTHER RESOLVED, That the 2022 Buildings Capital Improvement Program budget is hereby amended as follows:

 

Expense

Prior Project Savings (B70092)                                                                     ($200,000)

Law Enforcement Center Water Heater Replacements Project (B20040)     $200,000

Total Expense                                                                                                  $0

 

Revenue

Prior Project Savings (B70092)                                                                    ($200,000)

Law Enforcement Center Water Heater Replacements Project (B20040)    $200,000

Total Revenue                                                                                                  $0

end

 

PREVIOUS BOARD ACTION

22-101; 3/8/22

 

ATTACHMENTS

Attachment: Financial Summary

 

BOARD GOALS

   A Great Place to Live                                          A Healthy Environment     

   A Successful Place for Business and Jobs         Excellence in Public Service

 

PUBLIC ENGAGEMENT LEVEL

  Inform and Listen                Discuss                               Involve                               N/A

 

CONTACT

Department Head: Taud Hoopingarner

Author: Joe Lexa