Legislation Details

File #: DC-6011    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 9/14/2026 In control: Board of Commissioners
On agenda: 10/27/2026 Final action:
Enactment date: Resolution #:
Title: Amendment To 2026 Transportation Capital Improvement Program Budget For 117th Street (County State Aid Highway 32) Improvements, Rich Valley Boulevard (County State Aid Highway 71) To Court House Boulevard (Trunk Highway 52) In City Of Inver Grove Heights, County Project 3265
Sponsors: Transportation
Attachments: 1. Project Map
Date Ver.Action ByActionResultAction DetailsMeeting MaterialsVideo
No records to display.

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Amendment To 2026 Transportation Capital Improvement Program Budget For 117th Street (County State Aid Highway 32) Improvements, Rich Valley Boulevard (County State Aid Highway 71) To Court House Boulevard (Trunk Highway 52) In City Of Inver Grove Heights, County Project 32-65

end

 

RESOLUTION

body

WHEREAS, Dakota County (County), in cooperation with City of Inver Grove Heights (City), is proceeding with County Project (CP) 32-65 to reconstruct and realign 117th Street (County State Aid Highway 32) to improve safety, freight mobility, and corridor operations; and

 

WHEREAS, delivery of CP 32-65 requires the acquisition of multiple right-of-way parcels through negotiated settlements and condemnation proceedings administered through District Court, which include escrow deposits that delay reimbursement to the project; and

 

WHEREAS, several right-of-way settlements have required payments above initial appraisals due to updated valuations, severance considerations, and avoidance of potential litigation expenses, and these obligations must be paid as they are finalized; and

 

WHEREAS, construction-support services such as construction administration, materials testing, railroad coordination, and flagging continue to accrue at current 2026 market rates, and inflation has increased the cost of change orders, quantity adjustments, and other non-bid work necessary to deliver the project; and

 

WHEREAS, pending condemnation reimbursements from District Court and increased right-of-way and construction-support expenditures have created a funding gap within the current CP 32-65 budget, and maintaining timely financial authority is necessary to avoid delays in project delivery and coordination with external partners; and

 

WHEREAS, sufficient revenue exists within the Transportation Sales and Use Tax Fund to support a budget amendment to the 2026 Transportation Capital Improvement Program (CIP) to address these needs.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby amends the 2026 Transportation Capital Improvement Program Budget for County Project 32-65 by $1,805,900 from the Transportation Sales and Use Tax Fund; and

 

BE IT FURTHER RESOLVED, That the 2026 Transportation Capital Improvement Program Budget is hereby amended as follows:

 

Expense

County Project 32-65: $1,805,900 

Total Expense: $1,805,900

 

Revenue

Transportation Sales and Use Tax: $1,805,900

Total Revenue: $1,805,900

end

 

BACKGROUND

Dakota County, in partnership with City of Inver Grove Heights, is constructing CP 32-65 to reconstruct and realign 117th Street between County State Aid Highway 71 and Trunk Highway 52. Construction began in 2025 and will continue through the 2027 season. Work to date includes major roadway reconstruction, freight movement and safety enhancements, railroad crossing upgrades, drainage and utility improvements, installation of new trail and pedestrian facilities, and full corridor realignment. As for Pay Estimate No. 7, approximately 57% of the revised contract value has been completed, with $8,345,582 in work certified to date.

 

As the project advances, remaining right-of-way obligations are being resolved through negotiated settlements and, where necessary, condemnation proceedings consistent with Minnesota eminent domain statutes. Several industrial parcels have required settlement amounts above initial appraisals due to updated valuations, severance impacts, and the avoidance of potential litigation expenses. Required condemnation escrow deposits placed with district court have also temporarily delayed reimbursement revenue, resulting in short-term cash-flow constraints as right-of-way payments continue to be issued. A total of $2,078,600 was originally deposited with district court for eight parcels as part of condemnation proceedings. To date, $1,188,800 has been reimbursed to Dakota County following court actions. An estimated remaining escrow balance of $889,800 is held in district court until the final distribution when the funds will be released back to the County. Another $416,100 in right of way budget is required to total $1,305,900 for:

 

•                     Final right of way settlements still pending

•                     Valuation and severance adjustments

•                     Condemnation related legal and administrative costs

•                     Cash flow between required right of way payments and court reimbursement

 

Although the construction contract was awarded at a fixed bid price in December 2025, continued inflation during the 2026 construction season has required additional railroad costs and construction related services. It is estimated an additional budget amendment of $500,000 is required for:

 

•                     Railroad coordination services

•                     Railroad flagging

•                     Railroad observation

•                     Material testing

•                     Quantity adjustments

 

A total budget amendment of $1,805,900 is needed to ensure the County can continue to meet right-of-way settlement requirements, fund railroad and utility coordination activities, and maintain continuous construction progress through the 2026-2027 seasons. The amendment also offsets short-term cash-flow impacts from District Court escrow deposits and inflation-driven increases in construction support costs, helping preserve schedule, safety, and overall project delivery. $899,800 will be released by the court back to the County after final condemnation distribution is complete.

 

RECOMMENDATION

recommendation

Staff recommend that the Dakota County Board of Commissioners amend the 2026 Transportation Capital Improvement Program Budget for CP 32-65 to include an additional $1,805,900 from the Transportation Sales and Use Tax Fund.

end

 

FINANCIAL AND STAFFING IMPACTS

The 2026 Transportation Capital Improvement Program Budget currently includes $24,464,492 for CP 32-65. As of September 25, 2026, actual expenditures total $13,346,451, with an additional $10,685,998 committed, leaving a remaining available balance of $432,043.

 

This balance is insufficient to meet upcoming right-of-way settlement obligations, condemnation-related expenses, and construction-support costs that are now accruing. The difference between programmed right-of-way funding and actual costs totals $1,305,900, and an additional $500,000 is required to support construction-related cash-flow needs, resulting in a total shortfall of $1,805,900.

 

Sufficient revenue exists within the Transportation Sales and Use Tax Fund to fully support this amendment. No additional FTEs are required.

 

This amendment aligns with County budget compliance policies and ensures adequate budget authority to complete the project.

 

CP 32-65 New County Road 32/71 TH52 IGH Current Approved Budget (Before Amendment)

Funding Source

Approved Budget

Available Budget

Sales and Use Tax

$9,052,082

$432,043

City

$5,734,000

$0

Federal

$8,000,000

$0

Transportation Advancement Account

$1,678,410

$0

Total

$24,464,492

$432,043

 

CP 32-65 New County Road 32/71 TH52 IGH Proposed Amended Budget

Funding Source

Proposed Approved Budget

Proposed Available Budget

Sales and Use Tax

$10,857,982

$2,237,943

City

$5,734,000

$0

Federal

$8,000,000

$0

Transportation Advancement Account

$1,678,410

$0

Total

$26,270,392

$2,237,943

 

PREVIOUS BOARD ACTION

None.

 

ATTACHMENTS

Attachment: Project Map

 

CONTACTS

Department Director: Erin Laberee