Type: Regular Action Status: Agenda Ready
File created: 8/4/2022 In control: General Government and Policy Committee of the Whole
On agenda: 8/16/2022 Final action:
Enactment date: Resolution #:
Title: Award Of Bid And Authorization To Execute Contract With Donlar Construction Company For South St. Paul Library Project And Authorization To Increase Project Budget And Amend 2022 Buildings Capital Improvement Program And Non-Departmental Budgets
Sponsors: Parks, Facilities, and Fleet Management
Attachments: 1. Financial Summary, 2. Bid Tabulation, 3. Written Justification for the Use of ARP Funds

DEPARTMENT: Parks, Facilities, and Fleet Management

FILE TYPE: Regular Action

 

TITLE

title

Award Of Bid And Authorization To Execute Contract With Donlar Construction Company For South St. Paul Library Project And Authorization To Increase Project Budget And Amend 2022 Buildings Capital Improvement Program And Non-Departmental Budgets

end

 

PURPOSE/ACTION REQUESTED

Authorize execution of a contract with Donlar Construction Company to complete construction of the South St. Paul Library project. This project is included in the 2022-2026 Building Capital Improvement Program (CIP) Adopted Budget. Additionally, authorize amendment to the 2022 Building Capital Improvement Program and Non-Departmental Budgets to increase the total South St. Paul Library project budget to $11,300,000 and update its funding source.

 

SUMMARY

By Resolution No. 22-033 (January 18, 2022), the Dakota County Board of Commissioners approved the design of the proposed South St. Paul Library and authorized staff to negotiate the terms of a joint powers agreement (JPA) to complete the City library’s merger and acquisition of land for the County’s tenth branch library location.

 

By Resolution No. 22-281 (June 21, 2022), the Dakota County Board of Commissioners approved the JPA between the City of South St. Paul and Dakota County. The JPA was approved with the understanding that the Board would determine funding for the library prior to award of a construction contract.

 

Bid documents were prepared by staff with the professional design support of BKV Group. The project was formally advertised, and competitive bids were received on August 4, 2022. The three lowest bid totals evaluated for award are as follows:

                     Bidder                                                                                                                                                                                             Contract Amount

                     Donlar Construction Company, Shoreview, MN                                                               $8,434,500

                     Ebert Inc. - d.b.a. “Ebert Construction”, Corcoran, MN                                          $8,998,000

                     Jorgenson Construction, Inc., Minneapolis, MN                                                               $9,047,000

 

All bids received were complete, included a bid bond, and acknowledged the Addendums required for evaluation. The project included four Alternates to expose specific costs; three of these four were included in the totals above. All alternates are detailed in the Bid Tabulation attachment.

The original project funding was split evenly between County and State of MN Bonding funds. Although sought, the State Bonding funds were not granted. In lieu of the original funding plan, the County Board has chosen to fund the complete project with Federal ARP funds. Final Rule, 31 CFR Part 35, Subp. A, Section 35.6 (b) permits capital expenditures for projects “responding to the public health emergency or its negative impacts.” See the attached required written justification for the use of ARP funds for this capital expenditure. Furthermore, extraordinary material and energy inflation coupled with continuing labor shortages have driven construction costs up in excess of prior estimates; for the award of this bid and the execution of a contract with the above-named Contractor, and for the project to proceed further, $1,500,000 in additional funding is needed to augment the original $9,800,000 expected for the project.

 

RECOMMENDATION

recommendation

After reviewing the qualifications of the low bidder, staff recommends award to Donlar Construction Company as the lowest responsive and responsible bidder in an amount not to exceed $8,434,500. With this award, $147,500 of the $8,434,500 Contractor’s award total will be reimbursed to the County by the City of South St. Paul as established by the prior executed JPA. Note that this $147,500 is not included within the total project budget because it will be directly reimbursed to the County. Additionally, staff recommends an amended total project budget of $11,300,000 be approved by the Board and authorize this total to come from Federal ARP funds. This new Project Budget does not include funds to be reimbursed to the County by the City per the JPA.

end

EXPLANATION OF FISCAL/FTE IMPACTS

The Adopted 2022 Building CIP Budget includes a total of $4,700,000 for the South St. Paul Library project. Based on the June Budget Workshop, this project anticipated the use of $9,800,000 of ARP funds. With a total budget amendment of $11,300,000 from ARP funding, sufficient funds will exist to award this contract and for the project to proceed into construction (see Attachment: Financial Summary). The $4,700,000 allocated prior within the Building CIP will not be used for this project.

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, the South St. Paul Library project was included in the 2022-2026 Building Capital Improvement Program (CIP) Adopted Budget; and

 

WHEREAS, bid document and specifications were prepared by County staff and BKV Group; and

 

WHEREAS, seven competitive bids were received on August 4, 2022; and

 

WHEREAS, Donlar Construction Company has the lowest bid of $8,434,500 that includes Alternates 2, 3 & 4; and

 

WHEREAS, staff has reviewed the qualifications of the bidder and recommend award to Donlar Construction Company as the lowest responsive and responsible bidder in an amount not to exceed $8,434,500 for the South St. Paul Library project; and

 

WHEREAS, the inflationary costs of materials and energy, coupled with a continuing labor shortage in the construction industry, have unprecedently escalated the required total project budget to $11,300,000; and

 

WHEREAS, the City of South St. Paul will directly reimburse Dakota County for an additional $147,500 of budgetary funding to complete site remediations as established in the June 2022 Joint Powers Agreement; and

 

WHEREAS, external revenues to support this project’s funding were requested but not received; and

 

WHEREAS, Final Rule, 31 CFR Part 35, Subp. A, Section 35.6 (b) permits capital expenditures for projects “responding to the public health emergency or its negative impacts.”

 

WHEREAS, This new library will respond to critical needs, including the areas of health care, employment, and workforce development, in a community that has been disproportionately impacted by the pandemic, with cumulative case and hospitalization rates well above the state average.

 

WHEREAS, as approved by Resolution No. 22-281 (June 21, 2022), the Dakota County Board of Commissioners is committed to the intentions of a Joint Powers Agreement recently executed with the City of South St. Paul to both construct the County’s tenth branch library location and assume the City’s library system into the Dakota County Library system.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Parks, Facilities, and Fleet Management Director to execute a contract for the South St. Paul Library project to Donlar Construction Company, 550 Shoreview Park Road, Shoreview, MN 55126, in an amount not to exceed $8,434,500, subject to approval by the County Attorney’s office as to form.

 

BE IT FURTHER RESOLVED, That the 2022 Buildings CIP Budget is hereby amended as follows:

 

Expense

South St. Paul Library (B30040)                                          $6,600,000

Total Expense                                                                                                                              $6,600,000

 

 

Revenue

Dakota County ARP Funding                                           $11,300,000

State Bonding                                                                                              ($  2,350,000)

County Funding                                                                         ($  2,350,000)

Total Revenue                                                                          $   6,600,000

; and

 

BE IT FURTHER RESOLVED, That the 2022 Non-Departmental Budget is hereby amended as follows:

 

Expense

ARP Expense                                                                                                                    ($11,300,000)

Total Expense                                                                                    ($11,300,000)

 

Revenue

Dakota County ARP Funding                                          ($11,300,000)

Total Revenue                                                               ($11,300,000)

end

 

PREVIOUS BOARD ACTION

20-572; 11/17/20

21-321; 06/22/21

21-421; 08/24/21

22-006; 01/04/22

22-033; 01/18/22

22-281; 06/21/22

 

ATTACHMENTS

Attachment: Financial Summary

Attachment: Bid Tabulation

Attachment: Written Justification for the Use of ARP Funds

 

BOARD GOALS

   A Great Place to Live                                          A Healthy Environment     

   A Successful Place for Business and Jobs         Excellence in Public Service

 

PUBLIC ENGAGEMENT LEVEL

  Inform and Listen                Discuss                               Involve                               N/A

 

CONTACT

Department Head: Taud Hoopingarner

Author: Jay Biedny