Skip to main content
Dakota County Logo
File #: DC-5246    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 12/31/2025 In control: Board of Commissioners
On agenda: 2/3/2026 Final action:
Enactment date: Resolution #:
Title: Authorization To Execute Contract With SRF Consulting Group, Inc., For Construction Administration, Inspection, Surveying, And Material Testing Services For Improvements To County State Aid Highway 42 (145th Street) At Trunk Highway 52 Interchange In City Of Rosemount, County Project 42-174
Sponsors: Transportation
Attachments: 1. Project Location Map, 2. Proposal Evaluation Sheet
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Contract With SRF Consulting Group, Inc., For Construction Administration, Inspection, Surveying, And Material Testing Services For Improvements To County State Aid Highway 42 (145th Street) At Trunk Highway 52 Interchange In City Of Rosemount, County Project 42-174

end

 

PURPOSE/ACTION REQUESTED

Authorize execution of a contract with SRF Consulting Group, Inc., for construction administration, inspection, surveying, and material testing services for County Project (CP) 42-174, improvements to the County State Aid Highway (CSAH) 42 at Trunk Highway (TH) 52 interchange in the City of Rosemount.

 

SUMMARY

To provide a safe and efficient transportation system, Dakota County is improving the CSAH 42 interchange at TH 52. This project will improve intersection operations of the interchange ramps, make safety improvements, and provide for increased traffic levels.

 

The number of construction projects in 2026 is greater than the number of available staff to manage the projects. The County is seeking expertise from an engineering firm to provide the construction management, inspection, surveying, and material testing services so this project can be completed next year.

 

Transportation Department staff sent Request For Proposals (RFPs) to three professional engineering firms with expertise in this type of work. Two firms submitted proposals, which were evaluated by Transportation staff.

 

Engineering Firm                                                                                    Total Cost                                                               Cost/Hour

SRF Consulting Group, Inc.                                          $284,893                                                               $150.74

Sambatek, LLC                                                                                    $408,183                                                               $192.63

Apex Engineering Group, Inc.                                          Did not propose

 

RECOMMENDATION

recommendation

The proposal from SRF Consulting Group, Inc., highlights their strong technical expertise, staff, and experience with complex transportation projects and meets the requirements of this project. Construction management was estimated to cost 8.0 percent of the estimated construction cost of $3.64 million, which is $291,440. The construction services of $284,893 came in under at 7.8 percent.

 

The County Engineer recommends execution of a contract with SRF Consulting Group, Inc., ending in December 2027, for construction management and inspections services for CP 42-174.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The adopted Transportation Capital Improvement Program budget includes $6.15 million for the project using Local, State, and Transportation Sales Tax funds. The construction management and inspection costs will be shared with the City of Rosemount in accordance with County policy.

 

CP 42-174 CSAH 42 at TH 52 Interchange - Intersection Improvements

Funding Source

Total Budget

Available Budget

City of Rosemount

$883,500

$883,500

MN DOT

$2,400,000

$2,400,000

Sales and Use Tax

$2,866,500

$2,470,069

Total

$6,150,000

$5,753,569

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to provide a safe and efficient transportation system, Dakota County and the City of Rosemount are proceeding with County Project (CP) 42-174; and

 

WHEREAS, CP 42-174 is the improvement of County State Aid Highway (CSAH) 42 at Trunk Highway (TH) 52 Interchange; and

 

WHEREAS, the County is the lead agency for CP 42-174 with construction scheduled to begin in spring 2026; and

 

WHEREAS, the 2026 construction workload is greater than the number of available County staff; and

 

WHEREAS, an engineering firm with this specialty will provide construction management, inspection, surveying, and material testing in 2026; and

 

WHEREAS, the proposal from SRF Consulting Group, Inc., highlights their strong technical expertise, staff, and experience with complex transportation projects and meets the requirements of this project; and

 

WHEREAS, the requested construction management was estimated to cost 8.0 percent of the estimated construction cost, but the proposal submitted by SRF Consulting Group, Inc., came in under the estimate of 7.9 percent; and

 

WHEREAS, the Transportation Capital Improvement Program budget includes sufficient funding in 2026 for CP 42-174; and

 

WHEREAS, the County Engineer recommends execution of a contract with SRF Consulting Group, Inc., for construction management, inspection, surveying, and material testing services for CP 42-174 for actual costs.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Transportation Director to execute a contract with SRF Consulting Group, Inc., for construction management, inspection, surveying, and material testing services for CP 42-174 for $284,893, subject to approval by the County Attorney’s Office as to form.

end

 

PREVIOUS BOARD ACTION

None.

 

ATTACHMENTS

Attachment: Project Location Map

Attachment: Proposal Evaluation Sheet

 

BOARD GOALS

   Thriving People        A Healthy Environment with Quality Natural Resources

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Erin Laberee

Author: Jeannine Briol