Skip to main content
Dakota County Logo
File #: DC-3237    Version:
Type: Consent Action Status: Passed
File created: 3/12/2024 In control: Board of Commissioners
On agenda: 4/23/2024 Final action: 4/23/2024
Enactment date: 4/23/2024 Resolution #: 24-201
Title: Authorization To Execute Contract Amendment With Donlar Construction Company For Kaposia Library Project And Amend 2024 Buildings Capital Improvement Program Budget
Sponsors: Parks, Facilities, and Fleet Management
Attachments: 1. Financial Summary, 2. Summary List of Changes for Final Amendment

DEPARTMENT: Parks, Facilities, and Fleet Management

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Contract Amendment With Donlar Construction Company For Kaposia Library Project And Amend 2024 Buildings Capital Improvement Program Budget

end

 

RESOLUTION

body

WHEREAS, the 2024 Capital Improvement Program (CIP) Adopted Budget as amended for the Kaposia Library project is a total of $11,300,000; and

 

WHEREAS, the City of South St. Paul provided another $135,828.16 in reimbursable funding for the Kaposia Library project’s construction; and

 

WHEREAS, by Resolution No. 22-383 (September 6, 2022), the County Board approved the original contract in the sum of $8,434,500 with an award to Donlar Construction Company; and

 

WHEREAS, with the original contract authorization, staff was also authorized to execute up to $250,000 worth of post-award changes; and

 

WHEREAS, $249,638.16 in contract amendments have already been formally executed by way of that authorization; and

 

WHEREAS, an additional $269,820.00 worth of post-award changes are requested for authorization to complete a final contract amendment to the contract with Donlar Construction Company; and

 

WHEREAS, these project cost increases to the construction contract will be paid for with uncommitted funds available within the CIP budget for this project; and

 

WHEREAS, the total authorized contract amendments to this contract would then be $519,458.16 for reimbursement of all construction change orders on the project; and

 

WHEREAS, sufficient funds within the CIP budget for the project (1001295) are available for this amendment.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Parks, Facilities, and Fleet Management Director to execute an amendment with Donlar Construction Company, 550 Shoreview Park Road, Shoreview, MN 55126, in an amount not to exceed $269,820.00 for a total maximum contract total not to exceed $8,953,958.16, subject to approval by the County Attorney’s office as to form; and

 

BE IT FURTHER RESOLVED, That the 2024 Buildings CIP Budget is hereby amended as follows:

 

                     Expense

                     South St. Paul Library (1001295)                     $135,828.16

                     Total Expense                     $135,828.16

 

                     Revenue

                     South St. Paul Funding                     $135,828.16

                     Total Revenue                     $135,828.16