Title: Approval Of Conceptual Phasing And To Amend Professional Services Contract With ALLiiANCE For Empire Maintenance Facility Redevelopment
Sponsors: Facilities Management
Indexes: Yes
Code sections: 15 mins./ - 5 mins./ Total: 20 mins.
Attachments: 1. Conceptual Phases

DEPARTMENT: Facilities Management

FILE TYPE: Consent Action

 

TITLE

title

Approval Of Conceptual Phasing And To Amend Professional Services Contract With ALLiiANCE For Empire Maintenance Facility Redevelopment

end

 

RESOLUTION

body

WHEREAS, Phase One improvements were completed at the Empire Maintenance Facility in 2020, including only half of the proposed South Building; and

 

WHEREAS, an addition to the South Building was included in the 2024-2028 Building Capital Improvement Program Adopted Budget and funded in 2024; and

 

WHEREAS, a previously proposed project to develop a new maintenance facility in Hampton was not approved to proceed; and

 

WHEREAS, Capital Projects Management pledged to the Board to develop and present an alternate to the Hampton facility that would meet its objectives of closing the existing Hastings and Farmington Shops through a phased approach; and

 

WHEREAS, the Transportation Department requested to co-locate all department staff to the Empire Maintenance Facility to improve efficiency; and

 

WHEREAS, this project scope is trying to complete three goals: expand the South Building as previously planned and currently funded, incorporate that construction into a phased approach for maintenance facilities that were to be at Hampton, and explore co-locating all Transportation Department staff at the Empire Maintenance Facility; and

 

WHEREAS, ALLiiANCE was selected as the consultant firm to provide early phase design services for this project by Resolution No. 24-147 (March 26, 2024); and

 

WHEREAS, ALLiiANCE worked with a Core Planning Group to confirm the programmatic needs and develop conceptual phases of construction; and

 

WHEREAS, three conceptual phases were developed to meet short- and long-term equipment storage and staff needs for the Transportation, Fleet, Facilities Management, and Sheriff’s departments at the Empire Maintenance Facility; and

 

WHEREAS, two additional approaches were developed to meet Transportation Department staff needs to co-locate at the Empire Maintenance Facility; and

 

WHEREAS, staff recommends moving ahead with design for equipment storage Phase One and Two plus Transportation Department staff Approach A; and

 

WHEREAS, additional design efforts to confirm a project scope, schedule and budget are necessary; and

 

WHEREAS, ALLiiANCE has provided a fee proposal to provide full schematic design services for the recommended approach and to increase fees by $390,000; for a new not to exceed contract value of $529,050; and

 

WHEREAS, there are sufficient funds within the project budget to cover this contract increase.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby approves proceeding with the recommended conceptual designs as presented and authorizes the Facilities Management Director to execute a contract amendment to the professional services contract with ALLiiANCE, 400 Clifton Avenue S., Minneapolis, MN 55403 to increase professional design fees for the Empire Maintenance Facility Redevelopment, in an amount not to exceed $390,000, subject to approval by the County Attorney’s Office as to form.