Legislation Details

File #: DC-5883    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 8/18/2026 In control: Board of Commissioners
On agenda: 9/22/2026 Final action:
Enactment date: Resolution #:
Title: Authorization To Execute Contract With Nadeau Companies For Construction And Slope Repair On Mississippi River Greenway In Inver Grove Heights, County Project 2000599
Sponsors: Parks
Attachments: 1. Project Location Map, 2. Contract Summary Sheet
Date Ver.Action ByActionResultAction DetailsMeeting MaterialsVideo
No records to display.

DEPARTMENT: Parks

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Contract With Nadeau Companies For Construction And Slope Repair On Mississippi River Greenway In Inver Grove Heights, County Project 2000599

end

 

RESOLUTION

body

WHEREAS, to promote a safe and accessible trail system, Dakota County is proceeding with the slope repairs needed along the Mississippi River Greenway in Inver Grove Heights; and

 

WHEREAS, staff advertised the construction contract for County Project (CP) 2000599 on August 28, 2026; and

 

WHEREAS, Nadeau Companies submitted the lowest responsive, responsible bid in the amount of $365,497; and

 

WHEREAS, the adopted 2026-2030 Parks Capital Improvement Program Budget has sufficient funds to accommodate the construction contract.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the County Manager, or delegate, to execute a contract with Nadeau Companies for the construction work (County Project 2000599) associated with the Mississippi River Greenway segment in Inver Grove Heights, in an amount not to exceed $365,497 based on its low bid, subject to approval by the County Attorney’s Office as to form.

end

 

BACKGROUND

County Project (CP) 2000599 includes slope stabilization and repairs to a washout area along the Mississippi River Greenway (MRG) trail segment adjacent to Land O’ Lakes Inc.’s Purina Animal Nutrition Feed Mill parcel (Purina), as shown in the Attachment: Project Location Map. This segment of the MRG is a critical link in the trail alignment, connecting the Pine Bend Bluffs trailhead to Spring Lake Park Reserve.

 

The MRG trail segment in Inver Grove Heights has been a priority for Dakota County Parks’ slope stabilization and maintenance efforts for several years. However, steep bluffs, ravines, and sensitive slopes continue to experience erosion driven by high volumes of urban stormwater, and limited available land makes it difficult to implement new treatment or control measures. These conditions contribute to ongoing stability and water quality challenges along the City’s Mississippi River shoreline, highlighting the need for targeted erosion-reduction projects.

 

Timeline: The MRG slope repair is anticipated to begin construction in October 2026 and be completed within six weeks.

 

Bids Received:

 

Bidder

Bid Amount

Nadeau Companies

$ 365,497

Max Steininger, Inc.

$ 413,240

Eureka Construction, Inc.

$ 420,508

UrbanEdge, LLC

$ 456,747

JC Hallet Construction

$ 532,332

Veit & Company, Inc.

$ 608,694

Sunram Construction, Inc.

$ 614,312

Meyer Contracting, Inc.

$ 653,175

Urban Companies

$ 703,683

 

Nine bids were received. The engineer’s estimate for the construction of CP 2000599 is $505,410. The lowest responsive, and responsible bidder Nadeau Companies, with a bid of $365,497, which is 27.7% below the engineer’s estimate. Staff has reviewed the bids and determined that the low bid was competitive at the time of bidding.

 

RECOMMENDATION

recommendation

Staff recommends awarding the bid to Nadeau Companies for construction and slope repairs along the Mississippi River Greenway segment in Inver Grove Heights in the amount of $365,497 for CP 2000599.

end

 

FINANCIAL AND STAFFING IMPACTS

County Project 2000599 Mississippi River Greenway - Purina Slope Repairs, has sufficient funds available for this contract using existing set-aside resources. There is no additional staffing impact.

 

County Project 2000599 - Mississippi River Greenway - Purina Slope Repairs

Funding Sources

Total Budget

Available Budget

Parks County Program Aid (via Urgent/Unplanned set-aside)

$52,329

$0

Transportation Advance Account (via Greenway Preservation set-aside)

$381,061

$350,000

Transportation Fund (staff time chargeback)

$1,123

$0

Environmental Legacy Fund (via Veterans Memorial Greenway project 1000636 release)

$350,000

$350,000

Totals

$784,513

$700,000

 

PREVIOUS BOARD ACTION

None.

 

ATTACHMENTS

Attachment: Project Location Map

Attachment: Contract Summary Sheet

 

CONTACTS

Department Director: Niki Geisler

Author: Luisa Torres