Dakota County Logo
File #: DC-3783    Version:
Type: Consent Action Status: Sent to the Board
File created: 9/10/2024 In control: Board of Commissioners
On agenda: 10/29/2024 Final action:
Enactment date: Resolution #:
Title: Authorization To Execute Agreements With Union Pacific Railroad Company Related To Construction Of Minnesota River Greenway In Cities Of Burnsville And Eagan, County Project P00127
Sponsors: Parks, Facilities, and Fleet Management
Attachments: 1. Project Map

DEPARTMENT: Parks, Facilities, and Fleet Management

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Agreements With Union Pacific Railroad Company Related To Construction Of Minnesota River Greenway In Cities Of Burnsville And Eagan, County Project P00127

end

 

RESOLUTION

body

WHEREAS, the Minnesota River Greenway runs along the south side of the Minnesota River in Eagan and Burnsville, extending from I-35W in Burnsville to Lilydale Regional Park in Saint Paul; and

 

WHEREAS, by Resolution No. 11-516 (October 18, 2011), the Dakota County Board of Commissioners adopted the Minnesota River Greenway Plan; and

 

WHEREAS, the rapidly developing and robust recreational network that has developed in the area has created increased demand for the completion of the trail connection between the recently constructed Lone Oak Trail Head, the Cedar Nicols Trailhead, and the Minnesota River Greenway Black Dog Segment to the west; and

 

WHEREAS, construction of the Fort Snelling segment of the Minnesota River Greenway began in November 2023; and

 

WHEREAS, Dakota County is preparing to proceed with the construction of a pedestrian bridge for the Minnesota River Greenway necessary to complete the project and provide a crossing of the adjacent Union Pacific Railroad track for construction activities; and

 

WHEREAS, Dakota County has sought and received approval from Union Pacific Railroad Company to construct the pedestrian bridge through their right of way; and

 

WHEREAS, Dakota County has sought and received approval from Union Pacific Railroad Company for a temporary, at-grade crossing of their right of way to allow for construction access to the project area; and

 

WHEREAS, Union Pacific Railroad Company has identified a total of $257,500 in fees and construction costs associated with these agreements.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Physical Development Director to execute a public overpass agreement with Union Pacific Railroad Company to authorize the construction of a pedestrian bridge for the Fort Snelling segment of the Minnesota River Greenway; and

 

BE IT FURTHER RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Physical Development Director to execute a construction agreement with Union Pacific Railroad Company to authorize the construction of a construction access for the Fort Snelling segment of the Minnesota River Greenway.

end