Legislation Details

File #: DC-2463    Version:
Type: Consent Action Status: Passed
File created: 8/8/2023 In control: Board of Commissioners
On agenda: 3/26/2024 Final action: 3/26/2024
Enactment date: 3/26/2024 Resolution #: 24-154
Title: Authorization To Execute First Amendment To Contract With S.M. Hentges & Sons, Inc. And Amend 2024 Transportation Capital Improvement Program Budget In Cities Of Inver Grove Heights And Eagan, County Projects 26-54, 63-27
Sponsors: Transportation
Attachments: 1. Financial Summary, 2. Cost Increase Summary 26-54, 3. Location Map CP 26-54

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute First Amendment To Contract With S.M. Hentges & Sons, Inc. And Amend 2024 Transportation Capital Improvement Program Budget In Cities Of Inver Grove Heights And Eagan, County Projects 26-54, 63-27

end

 

RESOLUTION

body

WHEREAS, Dakota County (County) is constructing County Project 26-54 and County Project 63-27 in the City of Inver Grove Heights and City of Eagan (Cities); and

 

WHEREAS, to provide a safe and efficient transportation system, the County and the Cities have proceeded with County Project 26-54 and County Project 63-27; and

 

WHEREAS, County Project 26-54 will expand approximately two miles of County State Aid Highway (CSAH) 26 (Lone Oak Road in Eagan, 70th Street in Inver Grove Heights) from Trunk Highway (TH) 55 to TH 3 from an existing two-lane roadway rural section to a four-lane divided urban roadway; and

 

WHEREAS, County Project 63-27 will construct on a new alignment CSAH 63 (Argenta Trail) from CSAH 28 (Amana Trail) north to 65th Street and from 65th Street to old Argenta Trail (CSAH 63) to the north of CSAH 26; and

 

WHEREAS, on August 3, 2021, Dakota County awarded the bid and executed a contract with S.M. Hentges & Sons Inc. for $24,776,465.25; and

 

WHEREAS, the project is now substantially complete with only minor items of work and turf establishment remaining; and

 

WHEREAS, the construction contract has cost increases of $1,121,450 or 4.5 percent over the original contract amount; and

 

WHEREAS, the primary component of the cost increase is fuel escalation in the amount of $525,000; and

 

WHEREAS, construction cost increases include additional costs for excavation, grading, and hauling around existing utilities, installing additional select granular borrow at storm ponds, potholing around existing utilities, density incentive, and a quantity overrun on aggregate base; and

 

WHEREAS, staff recommends authorizing a contract amendment with S.M. Hentges & Sons, Inc. in the amount of $1,121,450 for construction cost increases and authorizing a budget amendment in the amount of $1,121,450.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Physical Development Director to execute a first amendment to the contract with S.M. Hentges & Sons, Inc. in the amount of $1,121,450 for increased costs, resulting in a total amount of $25,897,915.25 for County Projects 26-54 and 63-27, subject to approval by the County Attorney’s Office as to form; and

 

BE IT FURTHER RESOLVED, That the 2024 Transportation Capital Improvement Plan Budget is hereby amended as follows:

 

                     Expense

                     County Projects 26-54 and 63-27                     $1,121,450

                     Total Expense                     $1,121,450

 

                     Revenue

                     Transportation Fund                     $1,121,450

                     Total Revenue                     $1,121,450