Skip to main content
Dakota County Logo
File #: DC-4148    Version: 1
Type: Consent Action Status: Passed
File created: 1/6/2025 In control: Board of Commissioners
On agenda: 2/4/2025 Final action: 2/4/2025
Enactment date: 2/4/2025 Resolution #: 25-080
Title: Authorization To Execute Construction Contract With Eureka Construction, Incorporated, For Mississippi River Greenway Rosemount East In City Of Rosemount, Project P00109
Sponsors: Parks
Attachments: 1. Project Location Map, 2. Construction Cost Changes Summary

DEPARTMENT: Parks

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Construction Contract With Eureka Construction, Incorporated, For Mississippi River Greenway Rosemount East In City Of Rosemount, Project P00109

end

 

PURPOSE/ACTION REQUESTED

Authorize a new contract with Eureka Construction, Incorporated, (Eureka) to replace expired contract (DCA20844), which extends construction services into 2025 for County Project (CP) P00109. 

 

SUMMARY

To provide a safe and efficient greenway system, Dakota County is proceeding with CP P00109. County Project P00109 is the construction of a 2.4-mile segment of the Mississippi River Greenway (MRG) in Rosemount, and is the last remaining segment of the regional trail to be secured, designed, and constructed in order to connect the national MRG from Hastings to South St. Paul (Attachment: Project Location Map).

 

By Resolution No. 23-596 (December 19, 2023), the County Board authorized the award and execution of a contract with Eureka for construction services for CP P00109.

 

The original contract had an expiration date of November 30, 2024, and due to staff oversight the contract was inadvertently allowed to expire while scope and work required of Eureka, including 2025 punch list items, is still required to complete the CP P00109 construction project.

 

In addition to the contract expiration date, the construction project has seen cost increases and seven change orders that will increase the total contract value and require additional budget totally $573,862.94. Some of the key additional cost increases include the following:

 

                     Approved Change Orders: $311,239.70

                     Drainage & Stormwater: $68,985.46

                     Paving: $59,821.82

                     Railroad Flagging: $34,220.00

 

RECOMMENDATION

recommendation

Staff recommends the execution of a new contract with Eureka in the amount of $9,059,631.17, which includes a base cost increase of $573,862.94 and an additional contingency of $76,137.06 which is $650,000 more than the original contracted amount of $8,409,631.17.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The 2025 Parks Capital Improvement Budget includes a project budget of $11,234,141.73, with all funding budgeted in prior years. Sufficient funds within the project budget are available for this amendment.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to provide a safe and efficient greenway system, Dakota County is proceeding with County Project (CP) P00109, Mississippi River Greenway Rosemount East; and

 

WHEREAS, the Mississippi River Greenway (MRG) Rosemount East segment is the last remaining segment of the regional trail to be secured, designed, and constructed in order to connect the national MRG from Hastings to South St. Paul; and

 

WHEREAS, the MRG Rosemount East project includes the construction of 2.4 miles of trail from its connection with MRG Rosemount West to Spring Lake Park Reserve; and

 

WHEREAS, the County is the lead agency for the project; and

 

WHEREAS, by Resolution No. 23-596 (December 19, 2023), the County Board authorized a contract with Eureka Construction for construction of CP P00109; and

 

WHEREAS, the original contract expired on November 30, 2024, and additional construction activities remain to complete the project; and

 

WHEREAS, the construction contract has increases of $573,862.94 or 7 percent over the original contract amount; and

 

WHEREAS, the construction cost increases include additional costs for traffic control, grading and ditch correction, railroad crossing panels, turf establishment and fencing; and

 

WHEREAS, staff recommends executing a new contract with Eureka Construction to complete remaining construction activities in 2025 and increasing the contract by $650,000 from the original; and

 

WHEREAS, the 2025 Park’s Capital Improvement Program Budget has sufficient funds to accommodate the construction contract.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners authorizes the Physical Development Director to award a new contract with Eureka Construction to complete construction services for County Project P00109 in an amount not to exceed $9,059,631.17, subject to approval by the County Attorney’s Office as to form.

end

 

PREVIOUS BOARD ACTION

23-596; 12/19/23

 

ATTACHMENTS

Attachment: Project Location Map

Attachment: Construction Cost Changes Summary

 

BOARD GOALS

   A Great Place to Live                                          A Healthy Environment     

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Niki Geisler

Author: Tony Wotzka