DEPARTMENT: Information Technology
FILE TYPE: Consent Action
TITLE
title
Authorization To Execute Fiber Optic Indefeasible Right To Use Agreement With City Of Lakeville
end
PURPOSE/ACTION REQUESTED
Authorize the Deputy County Manager to execute a Fiber Optic Indefeasible Right To Use Agreement (IRU) with the City of Lakeville.
SUMMARY
The City of Lakeville desires to obtain from Dakota County the use of 12 strands of County-owned fiber to provide the City of Lakeville fiber connecting Lakeville Fairfield Water Tower to Lakeville City Hall. Dakota County desires to obtain from the City of Lakeville the use of 24 strands of City-owned fiber to connect Fairfield 800 MHz Radio Tower with a fiber cable. Segment details include:
Segment 1: This segment consists of 12 strands of Dakota County’s 288 fibers providing a route between a splice vault at NE of Kensington Blvd and Juniper Way and Lakeville City Hall. The City of Lakeville is allocated the following strands:
• Strands 61-72 of 288F at NE Kensington Blvd and Juniper Way spliced to
• Strands 61-72 of 288F at NW of Jacquard Avenue and 215th Street West spliced to
• Strands 61-72 of 288F at NE of Dodd Blvd and 215th Street West spliced to
• Strands 61-72 of 288F at NE of Cedar Avenue and 215th Street West spliced to
• Strands 61-72 of 288F at NE of Cedar Avenue and Lakeville Blvd spliced to
• Strands 61-72 of 288F at SE of Cedar Avenue and 202tnd Street West spliced to
Lakeville City Hall at 20195 Holyoke Avenue
Segment 2: This segment consists of 24 strands of the City of Lakeville’s 48 fibers providing a route between Lakeville’s Fairfield 800 MHz Water Tower at 11075 210th Street West, Lakeville and our existing fiber cable. Dakota County is allocated the following strands:
• Lakeville Fairfield 800 MHz Water Tower at 11075 210th Street West, Lakeville spliced to Strands 13-36 of 48F of Kensington Blvd and Juniper Way splice vault
Dakota County 2025 General Fund fund balance will be utilized to pay $9,094 for the total construction costs to connect existing fiber optic cable.
RECOMMENDATION
recommendation
Staff recommends the County Board authorize the Deputy County Manager to execute an IRU with the City of Lakeville. The City of Lakeville will obtain from Dakota County the use of 12 strands of County-owned fiber to provide the City of Lakeville fiber connecting Lakeville’s Fairfield Water Tower to Lakeville City Hall. Dakota County will obtain from the City of Lakeville the use of 24 strands of City-owned fiber to connect Fairfield 800 MHz Radio Tower with a fiber cable. end
EXPLANATION OF FISCAL/FTE IMPACTS
The Dakota County 2025 General Fund fund balance will be utilized to pay $9,094 for the total construction cost to connect existing fiber optic cable.
☐ None ☒ Current budget ☐ Other
☐ Amendment Requested ☐ New FTE(s) requested
RESOLUTION
body
WHEREAS, the City of Lakeville desires to obtain from Dakota County the use of 12 strands of Dakota County-owned fiber optic cable to provide fiber connecting Lakeville’s Fairfield Water Tower to Lakeville City Hall; and
WHEREAS, the City of Lakeville will be allocated the following strands:
• Strands 61-72 of 288F at NE Kensington Blvd and Juniper Way spliced to
• Strands 61-72 of 288F at NW of Jacquard Avenue and 215th Street West spliced to
• Strands 61-72 of 288F at NE of Dodd Blvd and 215th Street West spliced to
• Strands 61-72 of 288F at NE of Cedar Avenue and 215th Street West spliced to
• Strands 61-72 of 288F at NE of Cedar Avenue and Lakeville Blvd spliced to
• Strands 61-72 of 288F at SE of Cedar Avenue and 202tnd Street West spliced to
Lakeville City Hall at 20195 Holyoke Avenue
; and
WHEREAS, Dakota County desires to obtain from the City of Lakeville use of 24 strands of City of Lakeville-owned fiber optic cable to connect Fairfield 800 MHz Radio Tower with a fiber cable; and
WHEREAS Dakota County will be allocated the following strands:
• Lakeville Fairfield 800 MHz Water Tower at 11075 210th Street West, Lakeville, MN spliced to Strands 13-36 of 48F of Kensington Blvd and Juniper Way splice vault
; and
WHEREAS, Dakota County will utilize $9,094 from the Dakota County 2025 General Fund fund balance to pay for the construction costs to connect existing fiber optic cable; and
WHEREAS, a Fiber Optic Indefeasible Right To Use Agreement with the City of Lakeville is required for use of County fiber optic cable.
NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Deputy County Manager to execute an Indefeasible Right to Use Agreement with the City of Lakeville, subject to approval by the County Attorney’s Office as to form.
end
PREVIOUS BOARD ACTION
None.
ATTACHMENTS
Attachment: Indefeasible Right To Use Agreement
BOARD GOALS
☐ Thriving People ☐ A Healthy Environment with Quality Natural Resources
☐ A Successful Place for Business and Jobs ☒ Excellence in Public Service
CONTACT
Department Head: Tony Gomes
Author: Dan Ferber