Skip to main content
Dakota County Logo
File #: DC-3517    Version: 1
Type: Consent Action Status: Passed
File created: 6/5/2024 In control: Board of Commissioners
On agenda: 7/9/2024 Final action: 7/9/2024
Enactment date: 7/9/2024 Resolution #: 24-352
Title: Authorization To Award Bid And Execute Construction Contract With McNamara Contracting, Inc., And Execute Contract With SRF Consulting Group, Inc. For Construction Administration Services For Pedestrian Crossing Safety Improvements In Eagan And West St. Paul, County Project 97-217
Sponsors: Transportation
Attachments: 1. Project Location, 2. SRF Construction Admin Proposal

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Award Bid And Execute Construction Contract With McNamara Contracting, Inc., And Execute Contract With SRF Consulting Group, Inc. For Construction Administration Services For Pedestrian Crossing Safety Improvements In Eagan And West St. Paul, County Project 97-217

end

 

PURPOSE/ACTION REQUESTED

The purpose of this action is to award bid and authorize execution of a construction contract with McNamara Contracting, Inc., and also authorize execution of a contract with SRF Consulting Group, Inc. (SRF) to administer construction-related activities, including administration, inspection, and survey services for pedestrian crossing improvements in Eagan and West St. Paul, County Project (CP) 97-217 (Attachment: Project Location Map).

 

SUMMARY

To promote a safe and efficient transportation system, Dakota County is proceeding with County Project (CP) 97-217. The project includes pedestrian improvements at three locations: two locations in Eagan and one location in West St. Paul. The purpose of the project is to improve safety at these crossing locations by shortening pedestrian crossings and adding signage to improve drivers’ attention to crossing and pedestrian activity. Construction is planned to start in summer of 2024 and be substantially complete by December 2024.

 

County Project 97-217 construction bids were received and tabulated on July 2, 2024.

 

Five bidders submitted bids as follows:

 

Bid Name                                                                                     Total Amount                                          

McNamara Contracting Inc.                      $386,905.00                     

New Look Contracting Inc.                                          $418,510.50

Park Construction Company                     $443,126.25

JL Theis Inc.                                                                                    $505,506.50

Urban Companies LLC                                          $571,174.40                     

                     

Engineer’s Estimate                                                               $246,431.08

 

The lowest responsive and responsible bid for CP 97-217 is $386,905.00 from McNamara Contracting Inc., which is 57 percent over the engineer’s estimate of $246,431.08. Staff has reviewed the bids and determined that the bid was competitive at the time of bidding.

 

By Resolution No. 23-207 (May 23, 2023), the County Board authorized a contract with SRF Consulting Group, Inc. for construction administration services not to exceed the amount of $49,040.50 for CP 97-217. This contract (Contract #C0035928.1) expired on October 1, 2023, due to challenges in finalizing the plans for construction.

 

County staff is preparing for the project to be constructed in 2024. County construction staff is unavailable to administer the construction contract due to 2024 construction season project workload; therefore, staff requested SRF Consulting Group, Inc. to provide a revised proposal for the required construction administration services for the project. SRF Consulting Group, Inc. was the project consultant for preliminary and final design, therefore, staff has determined that their proposal is reasonable and provides the best transition from design to construction. SRF Consulting Group, Inc. would also be able to address any design revisions needed for final plan approvals.

 

SRF Consulting Group Inc. prepared an updated construction administration proposal based on the scope of work provided by the County in the amount of $51,714.00 (Attachment: SRF Construction Admin Proposal). There were also some additional design services needed to revise the final plans to prepare for construction included in the SRF final proposal in the amount of $18,712. The total proposal amount is $70,426.00. A construction administration contract is necessary to complete CP 97-217 construction in 2024 due to County staff construction season workloads. Sufficient funding is available for the contract.

 

RECOMMENDATION

recommendation

Staff recommends awarding the bid and authorizing execution of a construction contract with McNamara Contracting, Inc. in the amount of $386,905.00.

 

Staff also recommends authorizing a contract with SRF Consulting Group, Inc. for construction administration and design services in the amount of $70,426.00.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The adopted 2024 Transportation Capital Improvement Program Budget includes $625,000 for construction in 2024 including carryover from previous years for design, right of way acquisition, construction, and construction administration. There is currently $505,050.79 of funding remaining, which is sufficient funding for the contracts.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to provide a safe and efficient transportation system, Dakota County is proceeding with Dakota County Project (CP) 97-217; and

 

WHEREAS, CP 97-217 will construct pedestrian improvements at three locations, two in Eagan and one in West St. Paul; and

 

WHEREAS, the purpose and need for the project is to improve pedestrian safety at various intersections; and

 

WHEREAS, to address the purpose and need for the project, safety will be improved by shortening pedestrian crossings and adding signing to improve driver attention to crossing and pedestrian activity; and

 

WHEREAS, the County is the lead agency for the project; and

 

WHEREAS, construction is scheduled to begin in summer of 2024; and

 

WHEREAS, the 2024 Transportation Capital Improvement Program (CIP) Adopted Budget includes a total budget of $625,000 for CP 97-217, including carryover from previous years for design, right of way acquisition, construction, and construction administration; and

 

WHEREAS, pursuant to advertisement, five bids were received for CP 97-217 on July 2, 2024; and

 

WHEREAS, McNamara Contracting, Inc.’s bid in the amount of $386,905.00 was the lowest responsive and responsible bid received; and

 

WHEREAS, the 2024 CIP Adopted Budget includes sufficient funds for the Project; and

 

WHEREAS, staff recommends awarding the bid to McNamara Contracting, Inc.; and

 

WHEREAS, construction administration services are needed to complete construction in 2024; and

 

WHEREAS, By Resolution No. 23-207 (May 23, 2023), the County Board authorized a contract with SRF Consulting Group, Inc. for construction administration services not to exceed the amount of $49,040.50 for CP 97-217; and

 

WHEREAS, the previous contract with SRF Consulting Group, Inc. for construction administration services (Contract #C0035928.1) expired on October 1, 2023, due to challenges in finalizing the plans for construction; and

 

WHEREAS, SRF Consulting Group, Inc. was the project consultant for preliminary and final design, therefore, staff has determined that their proposal is reasonable and provides the best transition from design to construction; and

 

WHEREAS, staff requested SRF Consulting Group, Inc. provide a revised construction administration services proposal because County construction staff is unavailable due to the 2024 construction workload; and

 

WHEREAS, the cost of SRF Consulting Group, Inc. revised proposal to provide construction administration and final design services for CP 97-217 is $70,426.00; and

 

WHEREAS, the adopted 2024 CIP Adopted Budget includes sufficient funds for the construction administration services contract; and

 

WHEREAS, County staff recommends execution of a contract with SRF Consulting Group, Inc. for construction administration and design services for CP 97-217 in the amount of $70,426.00.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby awards the bid to and authorizes the Physical Development Director to execute the contract with McNamara Contracting, Inc. for County Project 97-217 in the amount of $386,905.00 based on their low bid, subject to approval by the County Attorney’s Office as to form; and

 

BE IT FURTHER RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Physical Development Director to execute the contract with SRF Consulting Group, Inc. to perform construction administration and design services for County Project 97-217 in an amount not to exceed $70,426.00, subject to approval by the County Attorney’s office as to form.

end

 

PREVIOUS BOARD ACTION

23-207; 3/28/23

 

ATTACHMENTS

Attachment: Project Location Map

Attachment: SRF Construction Admin Proposal

 

BOARD GOALS

   A Great Place to Live                                          A Healthy Environment     

   A Successful Place for Business and Jobs         Excellence in Public Service

 

CONTACT

Department Head: Erin Laberee

Author: Hassan Hussein