Legislation Details

File #: DC-5882    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 7/22/2026 In control: Board of Commissioners
On agenda: 9/1/2026 Final action:
Enactment date: Resolution #:
Title: Authorization To Execute Second Contract Amendment With Stahl Construction Company For Burnhaven Library Renovation
Sponsors: Facilities Management
Attachments: 1. Summary of Work Scope Changes
Date Ver.Action ByActionResultAction DetailsMeeting MaterialsVideo
No records to display.

DEPARTMENT: Facilities Management

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Second Contract Amendment With Stahl Construction Company For Burnhaven Library Renovation

end

 

RESOLUTION

body

WHEREAS, the amended 2026 Capital Improvement Program Adopted Budget for the Burnhaven Library Renovation project is a total of $8,575,000; and

 

WHEREAS, by Resolution No. 26-132 (March 24, 2026), the County Board approved the original contract with Stahl Construction Company, in the sum of $3,778,000; and

 

WHEREAS, staff has executed one contract amendment totaling $249,350.26 to amend the work scope since work began in April; and

 

WHEREAS, this second amendment totaling $263,409.19, will make the total of all changes $512,759.45, which surpasses the County limit for total changes in any one project before needing County Board approval; and

 

WHEREAS, by Resolution No. 26-160 (April 7, 2026), Library staff received external funding in the amount of $175,000, via a Library Construction Grant for this reading garden amenity from the Minnesota Department of Education; and

 

WHEREAS, two-thirds of the construction cost for this reading garden amenity will be paid for from the Minnesota Department of Education Grant; and

 

WHEREAS, the remaining third of the construction cost for this reading garden will be paid for with sufficient uncommitted funds available within the project budget.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the County Manager or delegate to execute a contract amendment with Stahl Construction Company, 861 Hennepin Avenue, Suite #200, Minneapolis, MN 55414, in an amount not to exceed $263,410, for a maximum contract total not to exceed $4,290,760 subject to approval by the County Attorney’s Office as to form.

end

 

BACKGROUND

The first amendment to the project added in large scope items as well as addressed the customary changes expected during a remodel of an existing building. The large scope increases include a complete renovation of the lobby public bathrooms which serve both the library and the License Center, new air handling equipment within areas not originally included, replacement of the penthouse ceilings with the addition of insulation, and sheetrock covering of existing spray foam insulation as required by the building official. These items will upgrade infrastructure throughout the entire building while taking advantage of its current closure to the public. The customary changes include unforeseen elements like replacement of the penthouse louvers, the addition of a unit heater at the penthouse, relocation of existing mechanical and electrical systems and other smaller issues. A full list of all changes related to these amendments can be found in Attachment: Summary of Work Scope Changes.

 

Like other exterior reading gardens incorporated into designs for Hastings, Kaposia, and Wentworth libraries in recent years, the reading garden construction within the second contract amendment to Stahl Construction will allow patrons direct access to an outdoor space for programmed events, reading, or meeting.

 

RECOMMENDATION

recommendation

Staff recommends authorizing a second contract amendment with Stahl Construction Company to increase the value by $263,410 for the Burnhaven Library Renovation project. This will increase the total contract value to $4,290,760.

 

Project 2000463 Burnhaven Library Design and Renovation

 

Funding Source

Total Approved Budget

Available Budget

General Obligation Capital Improvement Bonds, Series 2025A

$8,400,000

$2,648,955

Minnesota Department of Education Library Construction Grant

$   175,000

$   175,000

Total

$8,575,000

$2,823,955

 

end

 

FINANCIAL AND STAFFING IMPACTS

The 2026 Facilities Capital Improvement Program Adopted Budget as amended for the Burnhaven Library project is $8,575,000 and is funded almost entirely from the recent sale of County debt. $175,000 of this budget was funded from a Minnesota Department of Education Library Construction Grant. There is sufficient project budget available to fund this second contract amendment with Stahl Construction Company.

 

PREVIOUS BOARD ACTION

26-132; 03/24/26

26-160; 04/07/26

 

ATTACHMENTS

Attachment: Summary of Work Scope Changes

 

CONTACT

Department Director: Mike Lexvold

Author: Mike Lexvold