Skip to main content
Dakota County Logo
File #: DC-4934    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 9/22/2025 In control: Board of Commissioners
On agenda: 10/21/2025 Final action:
Enactment date: Resolution #:
Title: Authorization To Execute Joint Powers Agreements With City Of Apple Valley And City Of Rosemount For County State Aid Highway 42 (150th Street W) Mill And Overlay Project, County Project 42-173
Sponsors: Transportation
Attachments: 1. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Transportation
FILE TYPE: Consent Action

TITLE
title
Authorization To Execute Joint Powers Agreements With City Of Apple Valley And City Of Rosemount For County State Aid Highway 42 (150th Street W) Mill And Overlay Project, County Project 42-173
end

PURPOSE/ACTION REQUESTED
Authorize the Physical Development Director to execute joint powers agreements (JPAs) with the City of Apple Valley and the City of Rosemount for County Project (CP) 42-173.

SUMMARY
To provide a safe and efficient transportation system, the County is proceeding with CP 42-173, which includes Americans with Disabilities Act (ADA) improvements and the mill and overlay of County State Aid Highway (CSAH) 42 (150th Street W) from CSAH 33 (Diamond Path) to Trunk Highway (TH) 3 in the cities of Apple Valley and Rosemount (Attachment: Project Location Map). As part of the project, ADA-compliant upgrades will be made throughout the corridor, and the aging signal systems at CSAH 33 (Diamond Path) will be replaced. The project is scheduled for construction in 2027.

A JPA with each City is necessary to define County and City roles and responsibilities related to design, construction, and cost participation for CP 42-173. In accordance with Dakota County's cost share policy, the cost participation for ADA improvements, existing traffic signal replacement, and pavement preservation activities will be 100 percent County's responsibility.

RECOMMENDATION
recommendation
Staff recommends authorization to execute JPAs with the City of Apple Valley and the City of Rosemount for the mill and overlay of CSAH 42 (150th Street W) and the signal replacement at CSAH 33 (Diamond Path), CP 42-173.
end

EXPLANATION OF FISCAL/FTE IMPACTS
The 2025 Transportation Capital Improvement Program (CIP) Adopted Budget includes $327,995 in County State Aid Highway (CSAH) funds for engineering services related to CP 42-173. An additional $3,732,750 in CSAH funds and $216,000 in County funds is programmed in th...