Dakota County Logo
File #: DC-3967    Version: 1
Type: Consent Action Status: Passed
File created: 11/8/2024 In control: Board of Commissioners
On agenda: 12/17/2024 Final action: 12/17/2024
Enactment date: 12/17/2024 Resolution #: 24-626
Title: Authorization To Execute Safe Routes To Schools Program State Bond Grant Agreement From Minnesota Department Of Transportation For Improvements On 80th Street East In Inver Grove Heights, County Project 28-66
Sponsors: Transportation
Attachments: 1. Location Map, 2. Safe Routes to School Grant Letter
DEPARTMENT: Transportation
FILE TYPE: Consent Action

TITLE
title
Authorization To Execute Safe Routes To Schools Program State Bond Grant Agreement From Minnesota Department Of Transportation For Improvements On 80th Street East In Inver Grove Heights, County Project 28-66
end

PURPOSE/ACTION REQUESTED
Authorize execution of Safe Routes To Schools (SRTS) program state bond grant agreement No. 1058460 with the Minnesota Department of Transportation (MnDOT) for improvements to County State Aid Highway (CSAH) 28 (80th Street East), County Project 28-66, in Inver Grove Heights.

SUMMARY
County Project 28-66 in Inver Grove Heights will include the preliminary design for pedestrian and bicycle safety, SRTS improvements, and traffic signal improvements along CSAH 28 between Babcock Avenue and Boyd Avenue. This project was identified in the 2021 Dakota County Pedestrian Crossing Safety Assessment to provide improved pedestrian and bicyclist crossing infrastructure for community destinations along CSAH 28 in the project area. During project development, the SRTS crossing infrastructure improvements were separated into an independent plan set and a construction project to meet funding deadlines. This request for board action only refers to the SRTS plans of County Project 28-66.

A $250,000 Minnesota State SRTS grant was awarded to Dakota County in 2022 to fund crossing infrastructure improvements along CSAH 28 near Simley High School. A contractor must be awarded the construction contract to complete the grant agreement before the end of 2024 calendar year. If a grant agreement is not completed, the funds will be withdrawn. The project was advertised for construction bids on November 12, 2024, and bids were opened on December 9, 2024. The County Board authorized administrative award of the contract with Resolution No. 24-591, on December 3, 2024. Construction is scheduled for 2025.