File #: DC-3716    Version:
Type: Consent Action Status: Passed
File created: 8/14/2024 In control: Board of Commissioners
On agenda: 9/24/2024 Final action: 9/24/2024
Enactment date: 9/24/2024 Resolution #: 24-462
Title: Approval Of Schematic Design For Law Enforcement Center Boiler And Chiller Replacement Project
Sponsors: Parks, Facilities, and Fleet Management
Code sections: 15 mins. - / Total: 15 mins.
Attachments: 1. Schematic Design LEC Boiler and Chiller

DEPARTMENT: Parks, Facilities, and Fleet Management

FILE TYPE: Consent Action

 

TITLE

title

Approval Of Schematic Design For Law Enforcement Center Boiler And Chiller Replacement Project

end

 

RESOLUTION

body

WHEREAS, the 2024 Building Capital Improvement Program (CIP) Adopted Budget authorized the Law Enforcement Center (LEC) Boiler and Chiller Replacement project; and

 

WHEREAS, the design team, led by CMTA, met with the Core Planning Group five times to develop the schematic design for the LEC Boiler and Chiller Replacement project; and

 

WHEREAS, two steam boilers will be replaced with two hot water boilers; and

 

WHEREAS, two chillers will be replaced, but the existing cooling tower will be re-used; and

 

WHEREAS, 13 air handling units and steam piping will be converted to hot water; and

 

WHEREAS, staff recommends that the County Board approve the schematic design based on Option 2 of the Central Plant Study from June 2023, as presented by County staff to the Physical Development Committee of the Whole on September 17, 2024.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby approves the recommended schematic design for the Law Enforcement Center Boiler and Chiller Replacement as presented to the Physical Development Committee of the Whole on September 17, 2024.