DEPARTMENT: Transportation
FILE TYPE: Consent Action
TITLE
title
Approval Of Right Of Way Acquisition And Authorization To Initiate Quick-Take Condemnation For Intersection Improvements On County State Aid Highway 56 (Concord Boulevard) In City Of Inver Grove Heights, County Project 56-14
end
RESOLUTION
body
WHEREAS, to provide a safe and efficient transportation system, Dakota County is proceeding with County Project (CP) 56-14; and
WHEREAS, CP 56-14 is the design and construction of intersection, crossing safety, and accessibility improvements along CSAH 56 from Poplar Street to Coffman Avenue in the City of Inver Grove Heights; and
WHEREAS, Dakota County is the lead agency for design, construction administration, and right of way acquisition necessary in 2024 for construction to begin in the summer of 2025; and
WHEREAS, the acquisition of temporary and permanent easements from eight private property parcels is necessary, as identified in Attachment: Acquisition Maps; and
WHEREAS, the acquisition of the following eight (8) parcels is necessary to move forward with the project:
20-01400-54-014 - CF MH Skyline Fee, LLC - Parcel 1
A permanent easement for transportation purposes over, under, and across that part of the following described property:
That part of the Southwest Quarter of the Northwest Quarter, the Northwest Quarter of the Southwest Quarter, the Southwest Quarter of the Southwest Quarter and Government Lots 5, 6 and 7, Section 11, Township 27 North, Range 22 West, and that part of the Northwest Quarter of the Northwest Quarter and Government Lot 7, Section 14, Township 27 North, Range 22 West, all according to the Government Survey thereof, and described as follows: Commencing at the West Quarter corner of said Section 11; thence easterly, along the east-west center line of said Section 11, a distance of 740.52 feet to the center line of S.T.H. No. 56, said point being the actual point of beginning of the property to be described; ...
Click here for full text