Legislation Details

File #: DC-6027    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 9/18/2026 In control: Board of Commissioners
On agenda: 10/6/2026 Final action:
Enactment date: Resolution #:
Title: Authorization To Execute Contract With Collins Electrical Construction Company And Amend 2026 Adopted Budget For Temporary Signal Construction At County State Aid Highway 5 And Kenyon Avenue In Lakeville, County Project 05-060
Sponsors: Transportation
Attachments: 1. Project Location Map, 2. 05-060 RBA Contract Summary Sheet
Date Ver.Action ByActionResultAction DetailsMeeting MaterialsVideo
No records to display.
DEPARTMENT: Transportation
FILE TYPE: Consent Action

TITLE
title
Authorization To Execute Contract With Collins Electrical Construction Company And Amend 2026 Adopted Budget For Temporary Signal Construction At County State Aid Highway 5 And Kenyon Avenue In Lakeville, County Project 05-060
end

RESOLUTION
body
WHEREAS, Dakota County and the City of Lakeville are partnering on County Project (CP) 05-060 to provide a safe and efficient transportation system; and

WHEREAS, CP 05-060 includes installation of temporary traffic signals at the intersection of County State Aid Highway (CSAH) 5 and Kenyon Avenue; and

WHEREAS, Dakota County is the lead agency for CP 05-060, and construction is scheduled to occur in late 2026; and

WHEREAS, the temporary signal system will remain in operation until the construction of the Interstate 35, and CSAH 50/5 interchange is completed; and

WHEREAS, the project was publicly advertised, and three bids were received and tabulated on September 15, 2026; and

WHEREAS, the bid submitted by Collins Electrical Construction Company in the amount of $152,018, was the lowest responsive bid received from a responsible bidder; and

WHEREAS, the Transportation Capital Improvement Program (CIP) includes funds for CP 05-060 for construction in 2027, but it is more efficient to proceed with construction in 2026; and

WHEREAS, the 2026 Transportation CIP Budget requires an amendment to allow CP 05-060 to proceed with the contract award and construction in 2026; and

WHEREAS, the Safety and Management Set-aside fund balance contains sufficient funds to support the required budget amendment for CP 05-060 in the amount of $300,000; and

WHEREAS, cost participation for CP 05-060 will be shared between Dakota County (55%) and the City of Lakeville (45%); and

WHEREAS, staff recommends awarding the bid to Collins Electrical Construction Company.

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Coun...

Click here for full text