Skip to main content
Dakota County Logo
File #: DC-4033    Version:
Type: Consent Action Status: Passed
File created: 12/3/2024 In control: Board of Commissioners
On agenda: 1/21/2025 Final action: 1/21/2025
Enactment date: 1/21/2025 Resolution #: 25-044
Title: Authorization To Execute Contract With Bolton & Menk, Inc. For Construction Administration And Inspection Services For Minnesota River Greenway In Burnsville And Eagan, County Project P00127
Sponsors: Parks
Attachments: 1. Project Map, 2. Evaluation Summary

DEPARTMENT: Parks

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Execute Contract With Bolton & Menk, Inc. For Construction Administration And Inspection Services For Minnesota River Greenway In Burnsville And Eagan, County Project P00127

end

 

RESOLUTION

body

WHEREAS, by Resolution No. 11-516 (October 18, 2011), the Dakota County Board of Commissioners adopted the Minnesota River Greenway Plan; and

 

WHEREAS, Dakota County requires professional services for the administration and inspection for the construction of the pedestrian bridge over the Union Pacific Railroad track; and

 

WHEREAS, a request for proposals was released on November 25, 2024, for construction administration and inspection services; and

 

WHEREAS, three responses were received from qualified proposers; and

 

WHEREAS, Bolton & Menk, Inc. was identified as the most responsive to the request for proposals and within the project budget.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the Physical Development Director to execute a contract with Bolton & Menk, Inc. to provide construction administration services for the pedestrian bridge for the Fort Snelling Segment of the Minnesota River Greenway in Eagan in an amount not to exceed $666,423, subject to approval by the County Attorney’s Office as to form.

end