Type: Consent Action Status: Passed
File created: 7/31/2025 In control: Board of Commissioners
On agenda: 8/26/2025 Final action: 8/26/2025
Enactment date: 8/26/2025 Resolution #: 25-406
Title: Authorization To Amend Contract With Valley Paving, Inc., And Amend 2025 Capital Improvement Program Budget For 2025 Preservation Of Paved Highway Surface Project
Sponsors: Transportation
Attachments: 1. Location Map, 2. Cost Increase Summary
DEPARTMENT: Transportation
FILE TYPE: Consent Action

TITLE
title
Authorization To Amend Contract With Valley Paving, Inc., And Amend 2025 Capital Improvement Program Budget For 2025 Preservation Of Paved Highway Surface Project
end

PURPOSE/ACTION REQUESTED
Authorize a contract amendment with Valley Paving, Inc. for additional contract costs on the 2025 Preservation of Paved Highway Surface Project and amend the 2025 Capital Improvement Program (CIP) Budget.

SUMMARY
To promote a safe and efficient transportation system, Dakota County proceeded with the 2025 Preservation of Paved Highway Surface Project (Attachment: Location Map). The 2025 preservation work included resurfacing of County roads. The work began in June and will continue through October.

By Resolution No. 25-053 (January 21, 2025), the County Board authorized the County Manager or designee to award the Preservation of Paved Highway Surface Project to the lowest responsible bidder. The project was awarded to Valley Paving, Inc., in the amount of $5,576,946.12. Note that the contract amount was 16.5 percent under the Engineer's estimate.

Construction costs have increased by $349,803.44 or 6.3 percent due to a change in the design and higher quantities of pavement resurfacing. A list of item overruns is summarized in Attachment: Cost Increase Summary.

On County Project (CP) 11-32, MnDOT requested a change to the design of the pedestrian facility way to meet Americans with Disabilities Act (ADA) requirements for work within their right of way. County staff agreed to the design changes, which increased costs by an additional $225,823.13.

On County Project (CP) 91-34, there was an increase in milling and pavement quantities. The increased project cost due to the increase in quantities is $123,980.31.

RECOMMENDATION
recommendation
Staff recommends authorizing a contract amendment in the amount of $349,803.44 for a revised contract amount of $5,926,749.56 and a budget amendment in the amount of $3...