DEPARTMENT: Parks
FILE TYPE: Consent Action
TITLE
title
Authorization To Execute Contract With Nadeau Companies For Construction And Slope Repair On Mississippi River Greenway In Inver Grove Heights, County Project 2000599
end
RESOLUTION
body
WHEREAS, to promote a safe and accessible trail system, Dakota County is proceeding with the slope repairs needed along the Mississippi River Greenway in Inver Grove Heights; and
WHEREAS, staff advertised the construction contract for County Project (CP) 2000599 on August 28, 2026; and
WHEREAS, Nadeau Companies submitted the lowest responsive, responsible bid in the amount of $365,497; and
WHEREAS, the adopted 2026–2030 Parks Capital Improvement Program Budget has sufficient funds to accommodate the construction contract.
NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby authorizes the County Manager, or delegate, to execute a contract with Nadeau Companies for the construction work (County Project 2000599) associated with the Mississippi River Greenway segment in Inver Grove Heights, in an amount not to exceed $365,497 based on its low bid, subject to approval by the County Attorney’s Office as to form.
end
BACKGROUND
County Project (CP) 2000599 includes slope stabilization and repairs to a washout area along the Mississippi River Greenway (MRG) trail segment adjacent to Land O’ Lakes Inc.’s Purina Animal Nutrition Feed Mill parcel (Purina), as shown in the Attachment: Project Location Map. This segment of the MRG is a critical link in the trail alignment, connecting the Pine Bend Bluffs trailhead to Spring Lake Park Reserve.
The MRG trail segment in Inver Grove Heights has been a priority for Dakota County Parks’ slope stabilization and maintenance efforts for several years. However, steep bluffs, ravines, and sensitive slopes continue to experience erosion driven by high volumes of urban stormwater, and limited available land makes it difficult to implement new treatment or...