DEPARTMENT: Environmental Resources
FILE TYPE: Consent Action
TITLE
title
Authorization To Amend Contract With Stantec Consulting Services Inc. For Engineering Services For Construction Of Byllesby Dam Water-To-Wire Redevelopment Project
end
RESOLUTION
body
WHEREAS, Dakota County owns the Byllesby Dam and operates its high-hazard hydroelectric facility under the Federal Energy Regulatory Commission (FERC) safety regulations; and
WHEREAS, a complete turbine and powerhouse upgrade is being made to the 110-year-old facility; and
WHEREAS, to complete the upgrade, the Dakota County Board of Commissioners authorized execution of agreements for engineering services, construction, and construction engineering and administration; and
WHEREAS, by Resolution No. 15-532 (October 20, 2015), the Dakota County Board of Commissioners authorized execution of a contract with Ayres Associates, Inc., to complete engineering design for the turbine upgrade project; and
WHEREAS, by Resolution No. 19-773 (October 29, 2019), the Dakota County Board of Commissioners authorized execution of a contract with Boldt Construction, LLC, to complete construction of the project; and
WHEREAS, by Resolution 20-198 (April 21, 2020), the Dakota County Board of Commissioners authorized execution of a contract with Wenck Associates, Inc. (now part of Stantec Consulting Services, Inc., as of 2021) for on-site construction administration and engineering for an amount not to exceed $638,300; and
WHEREAS, Phase 1 of the project involved demolition of the existing powerhouse, which uncovered unanticipated sediment removals in the back bays and structural concrete mitigation not anticipated in the original contract; and
WHEREAS, a component of the project includes installation of a retaining wall for the adjacent substation for power distribution; and
WHEREAS, staff, in consultation with Stantec Consulting Services, Inc., has identified an opportunity to design a more cost-effective retaining wa...