File #: DC-5705    Version: 1
Type: Consent Action Status: Passed
File created: 5/13/2026 In control: Board of Commissioners
On agenda: 6/23/2026 Final action: 6/23/2026
Enactment date: 6/23/2026 Resolution #: 26-279
Title: Authorization To Execute Contract With Minger Construction Companies, Inc. And Related Grant Agreements And Amendment To 2026 Transportation Capital Improvement Program Budget For Multimodal Improvements On County State Aid Highways 28 And 56, County Projects 28-69 And 56-14
Sponsors: Transportation
Attachments: 1. Project Location Map - Combined Map for CP 56-14 (Concord Boulevard) and CP 28-69 (80th Street Trail Gap), 2. Mississippi River Greenway Completion Exhibit - From RAISE Grant Infrastructure Improvements Application
DEPARTMENT: Transportation
FILE TYPE: Consent Action

TITLE
title
Authorization To Execute Contract With Minger Construction Companies, Inc. And Related Grant Agreements And Amendment To 2026 Transportation Capital Improvement Program Budget For Multimodal Improvements On County State Aid Highways 28 And 56, County Projects 28-69 And 56-14
end

PURPOSE/ACTION REQUESTED
* Authorize execution of the construction contract with Minger Construction Companies, Inc. and related grant agreements.
* Amend the 2026 Transportation Capital Improvement Program (CIP) budget by $2,219,808 to fully fund project construction, contingency, and soft costs consistent with federal funding caps and joint powers agreement requirements.

SUMMARY
Dakota County is advancing two coordinated multimodal improvement projects-CP 28-69 and CP 56-14-that together complete a key segment of the Mississippi River Greenway (MRG) Phase 2. The project limits and planned improvements are illustrated in the Project Location Map (Attachment). An additional exhibit showing the Mississippi River Greenway system and project completion as included in the RAISE Grant Infrastructure Improvements application is provided for context (Attachment).

The projects will construct approximately 2.4 miles of multi-use trail, ADA improvements, enhanced pedestrian crossings, corridor safety elements, wayfinding, drainage upgrades, and associated roadway work along CSAH 28 and CSAH 56 in Inver Grove Heights and South St. Paul. Mississippi River Greenway Phase 2 includes:
? CP 28-69 - CSAH 28 (80th St.) Trail Gap
? CP 56-14 - CSAH 56 (Concord Blvd.) Pedestrian and Corridor Improvements

To maximize construction efficiency and manage federal funds under the same Federal Highway Administration (FHWA) authorization, the projects were bid together as State Project 019-090-027. Bids were received and tabulated on May 12, 2026. Seven bidders submitted bids as follows:

Bid Name Total Amount
Minger Construction Companies, In...

Click here for full text