Legislation Details

File #: DC-5770    Version: 1
Type: Consent Action Status: Agenda Ready
File created: 6/9/2026 In control: Board of Commissioners
On agenda: 7/7/2026 Final action:
Enactment date: Resolution #:
Title: Authorization To Execute Contract Amendment Five With Short-Elliott-Hendrickson, Incorporated To Provide Additional Engineering Services For Greenway Trail And Memorial Nodes Design For Veterans Memorial Greenway In Cities Of Inver Grove Heights And Eagan, County Project P00147 (1000636)
Sponsors: Parks
Attachments: 1. Project Location Map, 2. SEH Amendment Memorandum
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Parks
FILE TYPE: Consent Action

TITLE
title
Authorization To Execute Contract Amendment Five With Short-Elliott-Hendrickson, Incorporated To Provide Additional Engineering Services For Greenway Trail And Memorial Nodes Design For Veterans Memorial Greenway In Cities Of Inver Grove Heights And Eagan, County Project P00147 (1000636)
end

RESOLUTION
body
WHEREAS, the Veterans Memorial Greenway Project (P00147) will provide a link between Lebanon Hills Regional Park and the Mississippi River in central Dakota County and through the cities of Inver Grove Heights and Eagan; and

WHEREAS, the Veterans Memorial Greenway will include memorials along the trail, giving users the opportunity to learn about the sacrifices veterans have made over the years as they travel the trail; and

WHEREAS, by Resolution No. 20-430 (September 1, 2020), the County executed a contract with Short-Elliott-Hendrickson, Incorporated, for preliminary and final design engineering consulting services; and

WHEREAS, the County Board authorized four previous amendments to the contract for additional services; and

WHEREAS, a fifth amendment is proposed for additional services to complete phase 2 design (significant 90%-95% design updates, plan re-submissions, and additional permits), four enhanced memorial nodes design (Native American Veterans, Gold Star Families, Support Organizations, and Military Units and Flyers), and supplemental services to design phase 3 (topographic survey, wetland re-delineation, soil borings, Level 2 geometric layout, and railroad storm sewer license); and

WHEREAS, County staff recognizes and recommends the additional tasks as necessary to complete phase 2 design, the four enhanced memorial nodes design, and supplemental services to design phase 3; and

WHEREAS, staff negotiated an amount of $992,000 with Short-Elliott-Hendrickson, Incorporated, to complete the work; and

WHEREAS, the 2026 Parks Capital Improvement Program Budget includes sufficient fund...