Dakota County Logo
File #: DC-1520    Version: 1
Type: Consent Action Status: Passed
File created: 10/11/2022 In control: Board of Commissioners
On agenda: 1/3/2023 Final action: 1/3/2023
Enactment date: 1/3/2023 Resolution #: 23-021
Title: Authorization To Award And Execute Contract With McNamara Contracting And Amend 2023 Transportation CIP Budget For CP 9-56 On CSAH 9 In City Of Lakeville
Sponsors: Transportation
Attachments: 1. Project Location, 2. Financial Summary

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Award And Execute Contract With McNamara Contracting And Amend 2023 Transportation CIP Budget For CP 9-56 On CSAH 9 In City Of Lakeville

end

 

PURPOSE/ACTION REQUESTED

                     Award bid and authorize a contract with McNamara Contracting for County Project (CP) 9-56 in the City of Lakeville (City).

                     Amend the 2023 Transportation Capital Improvement Program (CIP) Budget.

 

SUMMARY

To provide a safe and efficient transportation system, Dakota County is proceeding with CP 9-56. County Project 9-56 is the construction of a new alignment of County State Aid Highway (CSAH) 9 (179th Street) from Hayes Avenue to CSAH 23 (Cedar Avenue) in the City of Lakeville (Attachment: Project Location). The segment of existing Dodd Boulevard between Hayes Avenue and CSAH 31 (Pilot Knob Road) will be reconstructed separately in 2024 as part of the jurisdictional transfer to the City.

 

Construction is planned to start in the spring 2023 and be substantially complete by November 2023. CP 9-56 was initially bid in May, 2022 and the bids were ultimately rejected with a plan to re-bid to allow for more flexible construction phasing and competitive bids. 

 

Construction bids were received and tabulated on December 6, 2022. Eight bidders submitted bids as follows:

                     Bidder                                                                                                         Bid Amount

                     McNamara Contracting                                          $11,207,634.63

                     Eureka Construction, Inc.                                          $11,634,920.41

                     Park Construction Company                     $11,981,260.74

                     Ryan Contracting Co.                                          $12,460,737.75

                     S.M. Hentges & Sons, Inc.                                          $12,636,123.65

                     Meyer Contracting, Inc.                                          $13,204,457.25

                     Max Steininger, Inc.                                                               $13,232,465.05

                     Northwest Asphalt                                                               $14,789,847.38

 

The lowest responsive and responsible bid for CP 9-56 is $11,207,634.63 from McNamara Contracting Inc., which is 3.45 percent under the engineer’s estimate of $11,608,521.70. The previous low bid from May 2022 was $11,669,790.53. Rebidding the project has resulted in a cost savings of $492,125.90 to both the City and County.

 

Staff and the Minnesota Department of Transportation (MNDOT) have reviewed the bids and determined that the bid was competitive at the time of bidding. In accordance with Minnesota Department of Transportation Standard Specifications for Construction, the contractor will be eligible for up to $100,000 incentive for actual pavement quality based on density and smoothness specifications. The incentive will be split in accordance with County policy for the respective roadway segment.

 

The total remaining project budget is $6,324,088 for CP 9-56 (Attachment: Financial Summary). The estimated total construction cost, including construction administration, signal materials, temporary storm sewer construction, pavement incentives, testing, and potential contract changes, is $13,050,441. The project cost has increased from the original budget due to added project scope and cost escalations. An amendment of $6,726,353 is requested to award the project.

 

The major amendment increases include:

-                     $1,881,000 for 179th Street segment roadway (aggregates and paving) and storm sewer (55% County, 45% City) due to construction price escalation and additional project scope.

-                     $1,805,000 for additional improvements along Cedar Ave, including new signal, roadway, storm sewer, and concrete items (85% County, 15% City). Cedar Ave changes were added to correct the intersection alignment and profile and to include milling and overlay.

-                     $1,150,354 for City sanitary sewer and water main replacement work on CP 9-56 (100% City cost).

-                     $817,000 Construction administration costs 55% County, 45% City).

 

Additional project costs are due to the need for three construction stages and cost escalation. Overall, the project cost is estimated to be split 60% County and 40% City. 

 

RECOMMENDATION

recommendation

Staff recommends awarding the bid to and authorizing execution of a contract with McNamara Contracting and amending the 2023 Transportation CIP budget. A budget amendment of $6,726,353 is requested to use $4,035,812 of Transportation fund balance and to increase the City share to $2,690,541 for CP 9-56.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The approved budget for CP 9-56 is $9,820,000 for project design, right of way acquisition, and construction. A budget amendment is requested in the amount of $6,723,353 which brings the total project budget to $16,546,353. Staff propose using $4,035,812 from Transportation fund balance for the County’s share and increasing the city share by $2,690,541.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, to provide a safe and efficient transportation system, Dakota County is proceeding with County Project (CP) 9-56; and

 

WHEREAS, the County is the lead agency for the Project, with construction scheduled for summer 2023; and

 

WHEREAS, the previously approved CP 9-56 budget is $9,820,000 for project design, right of way acquisition, and construction; and

 

WHEREAS, the remaining project budget is $6,324,088; and

 

WHEREAS, the bid of McNamara Contracting in the amount of $11,207,634.63 was the lowest responsive and responsible bid received; and

 

WHEREAS, the estimated total construction cost is $13,050,441, including pavement incentives, testing, and potential contract changes; and

 

WHEREAS, a budget amendment is necessary to account for the project costs above the Capital Improvement Program (CIP) amount and additional revenue from the City; and

 

WHEREAS, Dakota County currently has a sufficient transportation fund balance for the additional costs of the project; and

 

WHEREAS, the Minnesota Department of Transportation and the City concur in the award of a construction contract to McNamara Contracting, as the lowest responsive and responsible bidder; and

 

WHEREAS, the 2023 Transportation CIP budget for CP 9-56 shall be amended by $6,726,353; and

 

WHEREAS, staff recommends awarding the bid to and authorizing execution of a contract with McNamara Contracting and amending the 2023 Transportation CIP.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby awards the bid to and authorizes the Physical Development Director to execute the contract with McNamara Contracting for County Project 9-56 in the amount of $11,207,634.63 based on their low bid, subject to approval by the County Attorney’s Office as to form; and

 

BE IT FURTHER RESOLVED, That the contract amount may be increased by up to $100,000 for additional costs of pavement incentives met by McNamara Contracting, as specified in the contract documents; and

 

BE IT FURTHER RESOLVED, That the 2023 Transportation Capital Improvement Program Adopted Budget is hereby amended as follows:

 

Expense

CP 9-56                                                                                    $6,726,353

Total Expense                                                               $6,726,353

 

Revenue

City of Lakeville                                                               $2,690,541

Transportation Fund Balance                     $4,035,812

Total Revenue                                                               $6,726,353

end

 

PREVIOUS BOARD ACTION

22-241; 6/7/22

22-310; 7/19/22

 

ATTACHMENTS

Attachment: Location Map

Attachment: Financial Summary

 

BOARD GOALS

   A Great Place to Live                                          A Healthy Environment     

   A Successful Place for Business and Jobs         Excellence in Public Service

 

PUBLIC ENGAGEMENT LEVEL

  Inform and Listen                Discuss                               Involve                               N/A

 

CONTACT

Department Head: Erin Laberee

Author: Matthew Parent