File #: DC-1844    Version: 1
Type: Consent Action Status: Passed
File created: 1/30/2023 In control: Board of Commissioners
On agenda: 3/14/2023 Final action: 3/14/2023
Enactment date: 3/14/2023 Resolution #: 23-108
Title: Authorization To Award And Execute Contract With The Mathiowetz Construction Co. And Amend Transportation Budget For County State Aid Highway 47 And 85 Intersection Improvement, County Project 47-45
Sponsors: Transportation
Attachments: 1. Location Map, 2. Financial Summary

DEPARTMENT: Transportation

FILE TYPE: Consent Action

 

TITLE

title

Authorization To Award And Execute Contract With The Mathiowetz Construction Co. And Amend Transportation Budget For County State Aid Highway 47 And 85 Intersection Improvement, County Project 47-45

end

 

PURPOSE/ACTION REQUESTED

                     Award bid and authorize a contract with The Mathiowetz Construction Co. for County Project (CP) 47-45 in Vermillion Township.

                     Amend the adopted 2023 Transportation Capital Improvement Program (CIP) Budget

 

SUMMARY

To promote a safe and efficient transportation system, Dakota County is proceeding with CP 47-45, which is the reconstruction of the intersection of County State Aid Highway (CSAH) 47 (Northfield Boulevard) and 85 (Goodwin Avenue) in Vermillion Township (see Attachment: Location Map). The project was identified through the Rural Intersection Safety Assessment as the long-term approach to improve safety by correcting the skew of the intersection. Construction is scheduled for 2023.

 

Timeline: Construction is scheduled to begin this summer and be completed by late fall 2023.

 

Incentive: In accordance with Minnesota Department of Transportation Standard Specifications for Construction, the contractor will be eligible for up to a $50,000 incentive for actual pavement quality based on density and smoothness specifications. The pavement will be tested following highway construction to determine the amount of the incentive, if any.

 

Bids Received: Bids were received and tabulated on March 1, 2023. Six bidders submitted bids as follows:

 

                     The Mathiowetz Construction Co.                                          $2,749,492.76

                     Northland Grading & Excavating LLC                     $2,890,000.00

                     S.M. Hentges & Sons, Inc.                                                               $3,206,185.50

                     Valley Paving, Inc.                                                                                    $3,328,328.00

Meyer Contracting Inc.                                                               $3,421,258.18

Max Steininger, Inc.                                                                                    $4,266,708.91

 

The engineer’s estimate for CP 47-45 is $4,269,967.40. The lowest responsive and responsible bid is $2,749,492.76 from The Mathiowetz Construction Co., which is 35.6 percent under the estimate. Staff has reviewed the bids and determined that the low bid was competitive at the time of bidding.

 

The 2023-2027 Dakota County Capital Improvement Project (CIP) includes $500,000 for design and right of way (ROW) acquisition and $2 million for construction ($2.5 million total). The estimated total construction including pavement incentives ($50,000), testing ($13,747), and potential contract changes ($137,475) is $2,950,715. To date, design and ROW acquisitions costs are estimated at $223,780. Total estimated project cost (design, ROW, and construction) is $3,174,495. A budget amendment of $674,495 is requested.

 

RECOMMENDATION

recommendation

Staff recommends awarding the bid to and authorizing execution of a contract with The Mathiowetz Construction Co. and amending the 2023 Transportation CIP budget.

end

 

EXPLANATION OF FISCAL/FTE IMPACTS

The Adopted 2023 Transportation CIP includes $2,000,000 for construction. A budget amendment of $674,495 is requested to execute the construction contract. Sufficient funds exist in the Transportation Fund Balance for the additional funds needed to award the construction contract.

 

  None              Current budget              Other        

  Amendment Requested                           New FTE(s) requested

 

RESOLUTION

body

WHEREAS, Dakota County is proceeding with County Project (CP) 47-45; and

 

WHEREAS, CP 47-45 is the reconstruction of the intersection of County State Aid Highway (CSAH) 47 (Northfield Boulevard) and CSAH 85 (Goodwin Avenue) in Vermillion Township; and

 

WHEREAS, CP 47-45 is scheduled for construction in 2023; and

 

WHEREAS, the 2023 Transportation Capital Improvement Program (CIP) Adopted Budget includes $2,000,000 for the construction of CP 47-45; and

 

WHEREAS, the adopted 2023 Transportation CIP budget includes sufficient funds in its County Fund balance budget; and

 

WHEREAS, the bid of The Mathiowetz Construction Co. in the amount of $2,749,492.76 was the lowest responsive and responsible bid received; and

 

WHEREAS, The Mathiowetz Construction Co. will be eligible for up to a $50,000 incentive for constructing pavement that exceeds density and smoothness specifications; and

 

WHEREAS, the estimated total construction cost is $2,950,715, including pavement incentives, testing, and potential contract changes; and

 

WHEREAS, the 2023 Transportation Capital Improvement Program (CIP) Budget requires amendment for CP 47-45 in order to proceed with the construction contract; and

 

WHEREAS, the Transportation CIP County Fund balance contains sufficient funds to account for the budget amendment of CP 47-45 in the amount of $674,495 bringing the total project budget to $3,174,495; and

 

WHEREAS, staff recommends awarding the bid to and authorizing execution of a contract with The Mathiowetz Construction Co. and amending the 2023 Transportation CIP.

 

NOW, THEREFORE, BE IT RESOLVED, That the Dakota County Board of Commissioners hereby awards the bid and authorizes the Physical Development Director to execute a contract with The Mathiowetz Construction Co. for County Project 47-45 in the amount of $2,749,492.76 based on their low bid, subject to approval by the County Attorney’s Office as to form; and

 

BE IT FURTHER RESOLVED, That the contract amount may be increased by up to $50,000.00 for

additional costs of pavement incentives met by The Mathiowetz Construction Co., as specified in

the contract documents; and

 

BE IT FURTHER RESOLVED, That the 2023 Transportation Capital Improvement Program Adopted Budget is hereby amended as follows:

 

                     Expense

                     County Project 47-45                                          $674,475

                     Total Expense                                                               $674,475

 

                     Revenue

                     County Funds                                                               $674,475

                     Total Revenue                                                               $674,475

 

end

PREVIOUS BOARD ACTION

None.

 

ATTACHMENTS

Attachment: Location Map

Attachment: Financial Summary

 

BOARD GOALS

   A Great Place to Live                                          A Healthy Environment     

   A Successful Place for Business and Jobs         Excellence in Public Service

 

PUBLIC ENGAGEMENT LEVEL

  Inform and Listen                Discuss                               Involve                               N/A

 

CONTACT

Department Head: Erin Laberee

Author: Jenna Fabish