Motion: Mary Hamann-Roland
Ayes: 7
Second: Liz Workman
6.
Items Recommended by Board Committee*
Resolution No: 25-321
6.1
Authorization To Execute Third Contract Amendment With The Boldt Company
For Construction Manager/General Contractor Services For Phase II Of Byllesby
Dam Water-To-Wire Development Project And Amend Total Project Budget
Motion: Mary Hamann-Roland
Second: Liz Workman
WHEREAS, by Resolution No. 15-532 (October 20, 2015), the Dakota County
Board of Commissioners authorized staff to execute a contract for preliminary
design tasks on a turbine upgrade project to replace the existing century-old
equipment in the dam; and
WHEREAS, to complete this project, County staff developed a team including
an engineering consultant to provide project design, a turbine manufacturer to
provide turbine and generation equipment in a complete package (e.g.,
water-to-wire equipment), and a general contractor for installation of the
equipment and modification to the powerhouse structure; and
WHEREAS, due to the complexities in the design, construction, and installation
of the water-to-wire facilities, including new turbines and generators to maximize
the electric power output of the dam in the future, staff concluded that the
standard low bid methodology of awarding the construction contract was not
appropriate and was unlikely to provide the best value to the County; and
WHEREAS, by Resolution No. 18-538 (October 23, 2018), in accordance with
the authority granted in Minn. Stat. 130G.535, the County Board approved
utilizing a special type of contractor relationship that provides both construction
management and general contractor services on the project and allows staff to
develop and solicit a request for qualification for services; and
WHEREAS, by Resolution No. 19-773 (October 29, 2019), the Dakota County
Board of Commissioners authorized the execution of a contract with The Boldt
Company to perform Construction Manager/General Contractor Services related
to the redevelopment of the site for the project; and
WHEREAS, by Resolution No. 21-368 (July 20, 2021), the County Board
authorized the execution of a contract with The Boldt Company to perform
Construction Manager/General Contractor Services for Phase II of the
development project; and
WHEREAS, by Resolution No. 22-286 (July 19, 2022), the County Board
authorized the first amendment to the contract, bringing the total contract value
to a not-to-exceed amount of $22,652,875.42; and
WHEREAS, by Resolution No. 24-247 (May 21, 2024), the County Board
authorized the second amendment to the contract, bringing the total contract